2020 (1) TMI 1745
X X X X Extracts X X X X
X X X X Extracts X X X X
....4092 of 2016 whereby the High Court has partly allowed the said first appeals preferred by the original claimants and has enhanced the amount of compensation for the lands acquired, the acquiring body - The Executive Engineer, Nimna Dudhna Project has preferred the present appeals. 2. Learned Advocate appearing on behalf of the appellant has vehemently submitted that as such there was a delay of five and a half years in preferring the first appeals. It is submitted that assuming that the High Court is justified in enhancing the amount of compensation at par with the other land owners/claimants, as there was a huge delay of five and a half years, the High Court ought not to have saddled the interest liability for the period of delay upon ....
X X X X Extracts X X X X
X X X X Extracts X X X X
....Court ought not to have awarded the statutory benefits and the interest for the delayed period. 3.1 It is further submitted by the learned Advocate appearing on behalf of the respondents/original claimants that even otherwise as per the settled proposition of law, all claimants/land owners are entitled to the same compensation for the land acquired for the same project vide the same notification. 3.2 Making the above submissions, it is prayed to dismiss the present appeals. 4. We have heard the learned counsel for the respective parties at length. At the outset, it is required to be noted that the dispute in the present appeals is only with respect to award of statutory benefits and interest for the delayed period. It is not in ....
TaxTMI