Cases where this provision is explicitly mentioned in the judgment/order text; may not be exhaustive. To view the complete list of cases mentioning this section, Click here.
Provisions expressly mentioned in the judgment/order text.
Clandestine Removal - Supply of goods against ICB - sub-contractor of the main contractor - When the goods have been found to have been cleared towards the power project under ‘International Competitive Bidding’ which was eligible for duty exemption, the LOI and PO for the supply were addressed to IGP’s HO and there is no allegation of clandestine clearance etc, duty exemption benefit cannot be denied merely because the initial PAC was in the name of Kottivakkam unit and not in the name of Sembakkam unit on the date of clearance when the PAC was also rectified later. - AT
Note: It is a system-generated summary and is for quick reference only.