Appeal Restored After Factory Closure, Late Notice - Adjourned for Arguments The Appellate Tribunal CEGAT, New Delhi allowed the application for recalling the Final Order, dated 8-10-1999, restoring the appeal to its original ...
Cases where this provision is explicitly mentioned in the judgment/order text; may not be exhaustive. To view the complete list of cases mentioning this section, Click here.
Provisions expressly mentioned in the judgment/order text.
Appeal Restored After Factory Closure, Late Notice - Adjourned for Arguments
The Appellate Tribunal CEGAT, New Delhi allowed the application for recalling the Final Order, dated 8-10-1999, restoring the appeal to its original number. The factory was closed, and the notice for hearing was received late due to which the appeal was dismissed for non-prosecution. Adjourned for arguments to 26-7-2000.
The Appellate Tribunal CEGAT, New Delhi allowed the application for recalling the Final Order, dated 8-10-1999, restoring the appeal to its original number. The factory was closed, and the notice for hearing was received late due to which the appeal was dismissed for non-prosecution. Adjourned for arguments to 26-7-2000.