Just a moment...
Press 'Enter' to add multiple search terms. Rules for Better Search
Use comma for multiple locations.
---------------- For section wise search only -----------------
Accuracy Level ~ 90%
Press 'Enter' after typing page number.
Press 'Enter' after typing page number.
No Folders have been created
Are you sure you want to delete "My most important" ?
NOTE:
Press 'Enter' after typing page number.
Press 'Enter' after typing page number.
Don't have an account? Register Here
Press 'Enter' after typing page number.
Issues: (i) Whether levy and collection of building-workers welfare cess could operate before constitution of a Welfare Board, and whether subsequent operationalisation of the statutory machinery attracted the contractual subsequent-legislation clause; (ii) Whether cess could be retrospectively adjusted from amounts payable under an arbitral award in respect of a contract terminated before the Uttar Pradesh cess regime became operative; (iii) Whether the contractual foreign-currency price-adjustment formula permitted an additional 85% adjustment over the adjustable Euro component.
Issue (i): Whether levy and collection of building-workers welfare cess could operate before constitution of a Welfare Board, and whether subsequent operationalisation of the statutory machinery attracted the contractual subsequent-legislation clause.
Analysis: The welfare cess legislation was enacted to augment the resources of Welfare Boards. Although the enactments formally commenced on their notified dates, their effective operation required the statutory machinery for levy, collection, deposit and utilisation of cess, including constitution of Welfare Boards. In the absence of a Board, cess collected could not be transferred and applied for the statutorily intended welfare purpose. Constitution of the Board was therefore a condition precedent to levy and collection; registration of workers and provision of welfare benefits were not.
Analysis: Contractors could not reasonably include cess in bid prices when no enforceable collection mechanism existed at the relevant bid date. The subsequent establishment of the machinery and implementation of cess in the relevant States fell within the contractual framework for subsequent legislation. Mere inclusion of the enactments among labour laws in certain contracts did not alter this position. The arbitral interpretation was plausible, justified and neither perverse nor patently illegal, and did not warrant interference under the limited review available under the Arbitration and Conciliation Act, 1996.
Conclusion: The cess became leviable and collectible only after constitution of the relevant Welfare Board and operationalisation of the statutory machinery; the contractors were entitled to relief under the subsequent-legislation clause. This conclusion is in favour of the assessee.
Issue (ii): Whether cess could be retrospectively adjusted from amounts payable under an arbitral award in respect of a contract terminated before the Uttar Pradesh cess regime became operative.
Analysis: The contract had been entered into and terminated before Uttar Pradesh implemented the cess regime for ongoing projects. The cess issue was not raised during arbitration, the challenge proceedings, or review proceedings, and was raised only during execution to reduce the award liability. The contractor could not have factored a non-operative cess liability into its 2001 bid, and retrospective adjustment after termination of the contract was impermissible.
Conclusion: The contractor was not liable for cess in relation to the terminated contract, and the adjusted amount with award interest was required to be released. This conclusion is in favour of the assessee.
Issue (iii): Whether the contractual foreign-currency price-adjustment formula permitted an additional 85% adjustment over the adjustable Euro component.
Analysis: A harmonious reading of the payment and price-adjustment clauses showed that 85% of the Euro component was already adjustable, with 15% being non-adjustable. A further 85% adjustment would produce an impermissible compounded adjustment. The arbitral construction of the formula was reasonable, and no correction of an alleged contractual drafting error could be undertaken in arbitral-review proceedings.
Conclusion: The formula permitted adjustment only of 85% of the Euro component and not an additional 85% adjustment. This conclusion is in favour of the assessee.
Final Conclusion: The welfare cess could not be imposed on contractors for bid-period costs before the legally required Welfare Board and collection mechanism existed, and the reasoned arbitral constructions allocating the resulting burden were maintained.
Ratio Decidendi: Where a welfare cess is statutorily intended to fund Welfare Boards, constitution of the Board and operational statutory machinery are indispensable to its levy and collection; a plausible arbitral interpretation treating later operationalisation as subsequent legislation cannot be displaced in limited arbitral review.