Just a moment...
Press 'Enter' to add multiple search terms. Rules for Better Search
Use comma for multiple locations.
---------------- For section wise search only -----------------
Accuracy Level ~ 90%
Press 'Enter' after typing page number.
Press 'Enter' after typing page number.
No Folders have been created
Are you sure you want to delete "My most important" ?
NOTE:
Press 'Enter' after typing page number.
Press 'Enter' after typing page number.
Don't have an account? Register Here
Press 'Enter' after typing page number.
Issues: Whether, in the absence of a price-escalation clause in the original contract and in the presence of a supplemental agreement restricting enhanced rates, the contractor could still be awarded compensation for additional costs caused by delay, interruption of work, extra transport, and failure to provide a dumping site, and whether the arbitrator exceeded jurisdiction in granting such claims.
Analysis: The contract was delayed because the contractor was prevented from proceeding by law-and-order disturbances at the site, the required quarry material had to be procured from much farther locations, and no suitable dumping yard was provided. These circumstances increased the contractor's costs during the extended period of performance. The Court held that where the employer's failure to discharge its obligations directly causes delay and consequent extra expenditure, the arbitrator may compensate the contractor for the additional costs incurred in executing the work during the extended period. The supplemental agreement did not bar such relief when the claims arose from the actual consequences of the delay and the ground realities of performance.
Conclusion: The arbitrator did not exceed jurisdiction in allowing the escalation-related claims, and the High Court erred in setting aside the award on that basis. The appeal was therefore allowed and the arbitral award restored.