Just a moment...
Press 'Enter' to add multiple search terms. Rules for Better Search
Use comma for multiple locations.
---------------- For section wise search only -----------------
Accuracy Level ~ 90%
Press 'Enter' after typing page number.
Press 'Enter' after typing page number.
No Folders have been created
Are you sure you want to delete "My most important" ?
NOTE:
Press 'Enter' after typing page number.
Press 'Enter' after typing page number.
Don't have an account? Register Here
Press 'Enter' after typing page number.
Issues: (i) Whether, in proceedings under Section 33 read with Section 41 of the Arbitration Act, the Court could restrain the Union of India from withholding amounts due under other pending bills of the contractor; (ii) Whether clause 18 of the standard contract authorised the Union of India to recover or appropriate an unadjudicated claim for damages by adjusting sums due under other contracts.
Issue (i): Whether, in proceedings under Section 33 read with Section 41 of the Arbitration Act, the Court could restrain the Union of India from withholding amounts due under other pending bills of the contractor.
Analysis: Section 41(b) empowers the Court to make orders of interim injunction only for the purpose of, and in relation to, arbitration proceedings. An injunction restraining withholding of amounts due under other contracts would operate as a direction to pay those amounts, although the sums payable under such other bills were not the subject matter of the arbitration proceedings. Clause (a) of Section 41 applies the procedural provisions of the Code of Civil Procedure but does not confer an independent power to grant injunctions. An order which in substance compels payment cannot be sustained as an interim measure in aid of arbitration where the claim under the other contracts is outside the reference.
Conclusion: The Court held that such an injunction could not be granted and the contention of the contractor failed.
Issue (ii): Whether clause 18 of the standard contract authorised the Union of India to recover or appropriate an unadjudicated claim for damages by adjusting sums due under other contracts.
Analysis: Clause 18 was construed in the light of its language as a whole and in its contractual context. Although the words "any claim for the payment of a sum of money" are wide, they do not authorise appropriation of sums due to the contractor towards a mere disputed claim for damages before adjudication. The clause permits recovery or appropriation only where the claim has been admitted or established in the appropriate forum. On that construction, an order restraining recovery or appropriation would be within the permissible reach of the Court, but a restraint against withholding payment would not.
Conclusion: The Court held that clause 18 did not authorise appropriation of unadjudicated damages claims against the contractor's other pending bills.
Final Conclusion: The appeals were rejected because the impugned injunctions could not extend to withholding amounts under other bills, and the contractual clause did not permit adjustment of disputed damages claims before adjudication.
Ratio Decidendi: An interim injunction under Section 41(b) of the Arbitration Act must be confined to relief in aid of the arbitration proceedings themselves, and a disputed claim for damages cannot be appropriated against amounts due under other contracts until the claim is adjudicated or admitted.