AI TextQuick Glance (AI)Headnote
Issues: (i) Whether consideration received for milestone activities comprising project management plan, works programme, quality assurance plan and preliminary design was taxable as fees for technical services under Article 12(4) of the India-Germany DTAA and section 9(1)(vii) of the Income-tax Act, 1961. (ii) Whether interest under section 234B of the Income-tax Act, 1961 was chargeable from a non-resident assessee for the assessment year under appeal. (iii) Whether credit for tax deducted at source was to be allowed or restored for verification. (iv) Whether initiation of penalty proceedings under section 271(1)(c) of the Income-tax Act, 1961 was liable to be interfered with at this stage.
Issue (i): Whether consideration received for milestone activities comprising project management plan, works programme, quality assurance plan and preliminary design was taxable as fees for technical services under Article 12(4) of the India-Germany DTAA and section 9(1)(vii) of the Income-tax Act, 1961.
Analysis: The milestone activities formed part of a composite contract for design, manufacture, supply, testing, commissioning and related obligations for rolling stock. The apportionment of price into cost centres and milestones did not by itself convert the preparatory deliverables into independent services. The work done under the relevant milestones was held to be in the nature of submissions required for execution of the contract and was inextricably associated with the main supply obligation. Mere furnishing of plans, drawings, programmes and quality documents was found not to amount to managerial, technical or consultancy services within the treaty definition of fees for technical services.
Conclusion: The receipts for the relevant milestones were not taxable as fees for technical services; the issue was decided in favour of the assessee.
Issue (ii): Whether interest under section 234B of the Income-tax Act, 1961 was chargeable from a non-resident assessee for the assessment year under appeal.
Analysis: The governing legal position applied was that, for the relevant assessment year, the charging of interest under section 234B against a non-resident was not warranted in the circumstances considered by the Court. The later statutory amendment to section 209(1) was treated as prospective and not applicable to the year in question.
Conclusion: Interest under section 234B was held not leviable for the assessment year under appeal; this issue was decided in favour of the assessee.
Issue (iii): Whether credit for tax deducted at source was to be allowed or restored for verification.
Analysis: The claim for tax deducted at source credit required verification of the record by the Assessing Officer. The Tribunal did not finally quantify or decide the credit on merits and restored the matter for factual examination in accordance with law.
Conclusion: The issue was restored to the Assessing Officer for verification and appropriate grant of credit, if admissible.
Issue (iv): Whether initiation of penalty proceedings under section 271(1)(c) of the Income-tax Act, 1961 was liable to be interfered with at this stage.
Analysis: The challenge to penalty initiation was considered premature because no final penalty order had yet been passed. The issue therefore did not call for substantive interference on merits at that stage.
Conclusion: The challenge to initiation of penalty proceedings was rejected as premature.
Final Conclusion: The assessee succeeded on the principal transfer-pricing and interest issues, obtained remand on the tax deducted at source credit claim, and failed on the premature penalty challenge, resulting in partial relief overall.
Ratio Decidendi: Where milestone deliverables under a composite supply contract are merely preparatory and intrinsically connected to the main contractual obligation, they do not constitute fees for technical services absent a separate and independent rendering of managerial, technical or consultancy services; for the relevant period, interest under section 234B is not leviable against a non-resident in the manner considered here.
Composite contract milestone deliverables are not fees for technical services when they remain preparatory to the main supply obligation.
Milestone deliverables under a composite contract for design, manufacture, supply, testing and commissioning were held not to constitute fees for technical services because the project management plan, works programme, quality assurance plan and preliminary design were preparatory submissions intrinsically linked to the main supply obligation, not separate managerial, technical or consultancy services. Interest under section 234B was held not leviable against the non-resident assessee for the relevant year, with the later amendment to section 209(1) treated as prospective. Tax deducted at source credit was remanded for verification, while the challenge to initiation of penalty proceedings under section 271(1)(c) was rejected as premature.
Fee for Technical Services - design, plans, drawings provided by the assessee to Delhi Metro/DMRC - Scope of Article 12(4) of the India-Germany DTAA u/s.9(1)(vii) of the Income-tax Act, 1961 - rendering of services in the nature of managerial, technical and consultancy within the meaning of Article 12(4) of the DTAA - milestone payments - Work including designs was divided into cost centers - events represented by Milestones Al-Project Management Plan, A3-Works Programme, A5-Quality Assurance Plan and A10-Preliminary Design, which are inextricably linked to supply of Rolling Stock (RS2) to Delhi Metro Rail Corporation Limited (DMRC), are severable and thus chargeable to tax as FTS per Article 12 of the DTAA - assessee is a company incorporated in Germany HELD THAT:- After detailed examination of work under each milestone we are of considered view that the work achieved by the assessee under the aforesaid milestones does not fall within the meaning of managerial, technical or consultancy services. The assessee has merely furnished diagrams indicating organizational structure, qualification of personnel to be deployed etc. Work plan involves submission of proposed work programme and proposed design submission programme. Under quality assurance plan, the assessee is required to furnish the proposed method of achieving the Tenderer’s quality objectives with regard to requirement of the contract. The preliminary design activity requires the assessee to design the overall system and system configuration, identification of functioning of each system, sub-system, equipment, etc. In our humble view mere furnishing of plans, designs and drawings as mentioned above does not amount to rendering of services in the nature of managerial, technical and consultancy within the meaning of Article 12(4) of the DTAA. In any case, the plans, drawings and designs furnished by the assessee in compliance of Cost Center A1, A3, A5 and A10 is not an independent activity in itself. The said activity is only a stepping stone for achieving the ultimate object of supply, installation and maintenance of rolling stock. The activities underlined under Cost Center A are inextricably associated with design, execution and installation of rolling stock. In so far as the argument of the Department that since the payments for each Cost Center are allocated, therefore, the activity for each Cost Center is severable, we are not in agreement with the said argument with respect to “Cost Centre A”. The apportionment of the Cost for each milestone under each Cost Center is a pre-requisite of the Tender conditions. The activities/milestones detailed under Cost Centre A do not give rise to separate independent activity that can be severed from the main object. Furnishing of plans, drawings and designs as required in Cost Center A is primarily to ensure that the assessee has understood the final task and the path to be followed for reaching the final objective ensuring tenderer’s requirement and ensuring quality checks. Furnishing of plans, designs, etc. as envisaged in Cost Center A is only a step in the direction of commencement of rendering of service and Milestone A1, A3, A5 and A10 are preparatory. In so far as other Cost Centers are concerned, the activities under each Cost Center have to be examined for determining whether they are in the nature of technical, managerial or consultancy services within the meaning of Article 12(4) of India-Germany DTAA and whether they are dissociable? - The nature of activities carried out by the assessee so far in Cost Center A and in particular to milestones A1, A3, A5 and A10 are not in the nature of managerial, technical and consultancy services. So the payments for the same does not fall within the ambit of FTS as defined in Article 12(4) of the DTAA. Hence, in our considered view the decision in the case of Rio Tinto Technical Services [2012 (1) TMI 5 - DELHI HIGH COURT] does not support the cause of Revenue. Ergo, ground no. 1 to 3 of the assessee’s appeal are allowed. Charging of interest u/s. 234B - We find that the Hon’ble Supreme Court of India in the case of DIT vs. Mistibushi Corporation [2021 (9) TMI 875 - SUPREME COURT] has held that the proviso to section 209(1) of the Act inserted by Finance Act, 2012 would operate prospectively after AY 2012-13. Hence, for the assessment year under appeal i.e. AY 2008-09 no interest shall be chargeable from the assessee, a non-resident u/s. 234B of the Act. Thus, the assessee succeeds on ground no. 4 of appeal as well.