Opportunity to respond to jurisdictional reports is mandatory before customs settlement duty enhancement; connected applications require consistent ad...
Specific customs headings for scaffolding components prevail over general classification, invalidating misclassification proceedings and enabling with...
TDS u/s 194J OR 194C - The amounts paid to sub-contractors is either for erection, installation, fabrication, commissioning, testing & trial operation of some parts of the Power Plant and therefore cannot be termed as technical services as per the definition in Explanation 2 to section 9 (1) (vii). - AT
TDS u/s 194J OR 194C - The amounts paid to sub-contractors is either for erection, installation, fabrication, commissioning, testing & trial operation of some parts of the Power Plant and therefore cannot be termed as technical services as per the definition in Explanation 2 to section 9 (1) (vii). - AT