Customs valuation and classification require comparable evidence and assessment of imported goods in their actual condition, invalidating related pena...
Terminal gate verification for transshipment containers shifts to operators, while Customs controls and discrepancy reporting requirements remain mand...
TDS u/s 194J OR 194C - The amounts paid to sub-contractors is either for erection, installation, fabrication, commissioning, testing & trial operation of some parts of the Power Plant and therefore cannot be termed as technical services as per the definition in Explanation 2 to section 9 (1) (vii). - AT
TDS u/s 194J OR 194C - The amounts paid to sub-contractors is either for erection, installation, fabrication, commissioning, testing & trial operation of some parts of the Power Plant and therefore cannot be termed as technical services as per the definition in Explanation 2 to section 9 (1) (vii). - AT