Arrest safeguards and transit remand requirements invalidated detention following inter-State transfer without communicated grounds or magistrate auth...
Arrest safeguards require disclosed grounds, relative intimation and transit remand, while duplicate prosecution under the CGST framework is unsustain...
Document Identification Number defects can invalidate GST assessments, with delayed challenges entertained conditionally where patent irregularities e...
Windmill commissioning evidence supported higher depreciation where grid connection and electricity generation proved operational use before the relev...
Pharmaceutical promotion and transfer-pricing comparability principles limited disallowances, while uncorroborated search allegations and unsupported ...
Extended limitation under section 28(4) of the Customs Act could not be invoked where the bill of entry disclosed the tariff item and described the imported software CD as relatable to the LRSAM system, and the show cause notice relied only on an allegation of misdeclaration. The Tribunal held that invocation of the extended period requires a deliberate misstatement or suppression made with intent to evade duty, and that intent was not established, particularly given the appellant's status as a public sector undertaking engaged in defence supplies. As the demand rested entirely on the extended period, it failed. The consequential penalty under section 114A also failed because its foundation was the same as the extended-period allegation.
Extended limitation under section 28(4) of the Customs Act could not be invoked where the bill of entry disclosed the tariff item and described the imported software CD as relatable to the LRSAM system, and the show cause notice relied only on an allegation of misdeclaration. The Tribunal held that invocation of the extended period requires a deliberate misstatement or suppression made with intent to evade duty, and that intent was not established, particularly given the appellant's status as a public sector undertaking engaged in defence supplies. As the demand rested entirely on the extended period, it failed. The consequential penalty under section 114A also failed because its foundation was the same as the extended-period allegation.