Windmill commissioning evidence supported higher depreciation where grid connection and electricity generation proved operational use before the relev...
Pharmaceutical promotion and transfer-pricing comparability principles limited disallowances, while uncorroborated search allegations and unsupported ...
Business expenditure substantiation supports scrap credits, statutory payments and expense claims, while depreciation requires proof of actual busines...
The appellate authority had no power to condone delay beyond the statutory limit under Section 107, so its refusal to entertain the belated appeal was upheld. The High Court, however, found that the original adjudication order had not been properly communicated and the petitioner should not be left without a remedy. Exercising writ jurisdiction under Article 226 and applying the principle recognised in Tecnimont Private Limited, the Court condoned the delay independently, permitted revival of the appeal, and directed that the matter be decided on merits in accordance with law.
The appellate authority had no power to condone delay beyond the statutory limit under Section 107, so its refusal to entertain the belated appeal was upheld. The High Court, however, found that the original adjudication order had not been properly communicated and the petitioner should not be left without a remedy. Exercising writ jurisdiction under Article 226 and applying the principle recognised in Tecnimont Private Limited, the Court condoned the delay independently, permitted revival of the appeal, and directed that the matter be decided on merits in accordance with law.