Drawings/designs supply and erection supervision fees from German contractor: designs non-taxable; supervision taxed as FTS/PE depending on six-month ...
Imported analyser diagnostic cartridges treated as accessories with analyser system, not standalone diagnostic reagents; extended limitation and penal...
Steel-timber construction shuttering/formwork tariff classification dispute: essential character held steel, classified as shuttering under Heading 73...
A liquidation claim filed after a 787-day delay was rejected because Regulation 12(2)(b) requires claims to be lodged or updated within the prescribed time, and insolvency law treats timeliness as central to the liquidation process. Even if the timeline were treated as directory, an inordinate delay still needed a satisfactory explanation, which was absent here. The pendency or abatement of customs proceedings did not bar filing the claim before the liquidator, and a government department was not entitled to any special indulgence in condonation of delay. Entertaining the belated claim at an advanced stage would disrupt the liquidation process, so the rejection was upheld.
A liquidation claim filed after a 787-day delay was rejected because Regulation 12(2)(b) requires claims to be lodged or updated within the prescribed time, and insolvency law treats timeliness as central to the liquidation process. Even if the timeline were treated as directory, an inordinate delay still needed a satisfactory explanation, which was absent here. The pendency or abatement of customs proceedings did not bar filing the claim before the liquidator, and a government department was not entitled to any special indulgence in condonation of delay. Entertaining the belated claim at an advanced stage would disrupt the liquidation process, so the rejection was upheld.