Condonation of Delay: directoral disputes and pending company proceedings can constitute reasonable cause, allowing a belated return to be treated as ...
Revisionary jurisdiction under section 263 upheld; faceless assessments subject to revision when AO fails requisite enquiries, remitted for fresh asse...
Page of 4809
Press 'Enter' after typing page number.
5101 to 5120 of 96174 Results
❮
❯
❯❯
0 / 200
Expand Note
Add to Folder
No Folders have been created
+
Are you sure you want to delete "My most important" ?
Allowability of contractual damages claimed as expenses under section 37 was decided by ITAT: the Tribunal held that sums deducted by the government for late supply were compensatory damages for breach of contract and not payments for an "offence" or activity prohibited by law, so Explanation to section 37 did not apply. The Tribunal reasoned that mere failure to meet contractual timelines does not constitute a crime; the payments were incurred wholly and exclusively for business and therefore deductible as business expenditure, allowing the appeal and setting aside the disallowance.
Allowability of contractual damages claimed as expenses under section 37 was decided by ITAT: the Tribunal held that sums deducted by the government for late supply were compensatory damages for breach of contract and not payments for an "offence" or activity prohibited by law, so Explanation to section 37 did not apply. The Tribunal reasoned that mere failure to meet contractual timelines does not constitute a crime; the payments were incurred wholly and exclusively for business and therefore deductible as business expenditure, allowing the appeal and setting aside the disallowance.