Arrest safeguards and transit remand requirements invalidated detention following inter-State transfer without communicated grounds or magistrate auth...
Arrest safeguards require disclosed grounds, relative intimation and transit remand, while duplicate prosecution under the CGST framework is unsustain...
Document Identification Number defects can invalidate GST assessments, with delayed challenges entertained conditionally where patent irregularities e...
Windmill commissioning evidence supported higher depreciation where grid connection and electricity generation proved operational use before the relev...
HC determined that the respondent authority misconstrued the GST notification's applicability. The court held that paragraph 3(iv) of the notification applies exclusively to pre-GST contracts and cannot be used to deny reimbursement for contracts executed after July 1, 2017, which are governed by paragraph 4. The HC directed the public works department secretary to revisit the petitioner's claim regarding GST payment against gross bills from July 1, 2017 to March 31, 2019, in accordance with GST law, effectively remanding the matter for reconsideration and potential reimbursement.
HC determined that the respondent authority misconstrued the GST notification's applicability. The court held that paragraph 3(iv) of the notification applies exclusively to pre-GST contracts and cannot be used to deny reimbursement for contracts executed after July 1, 2017, which are governed by paragraph 4. The HC directed the public works department secretary to revisit the petitioner's claim regarding GST payment against gross bills from July 1, 2017 to March 31, 2019, in accordance with GST law, effectively remanding the matter for reconsideration and potential reimbursement.