Governmental authority status supports construction-service exemption, while pre-cutoff contract and stamp-duty compliance requires verification on re...
Automated Free Sale and Commerce Certificates enable paperless processing while retaining risk-based manual verification for selected exporter applica...
Employee stock-shortage penalties do not constitute consideration for services, preventing GST collection under Schedule II in employment relationship...
The CESTAT dismissed the appeal as it was filed after more than 30 months from receipt of the Order-In-Original, far exceeding the statutory time limit. Even considering the benefit of the Supreme Court's order dated 10.01.2022 in Suo Motto Writ Petition, the appeal remained significantly delayed. The Commissioner (Appeals) lacked authority to condone delays beyond 30 days as per Section 35 of the Central Excise Act, following the Supreme Court's precedent in Singh Enterprises. The Tribunal rejected the appellant's explanation for delay, finding insufficient cause shown for the extraordinary delay, and upheld the Commissioner (Appeals)' decision to dismiss the appeal for being time-barred under Section 85(3A) of the Finance Act, 1994.
The CESTAT dismissed the appeal as it was filed after more than 30 months from receipt of the Order-In-Original, far exceeding the statutory time limit. Even considering the benefit of the Supreme Court's order dated 10.01.2022 in Suo Motto Writ Petition, the appeal remained significantly delayed. The Commissioner (Appeals) lacked authority to condone delays beyond 30 days as per Section 35 of the Central Excise Act, following the Supreme Court's precedent in Singh Enterprises. The Tribunal rejected the appellant's explanation for delay, finding insufficient cause shown for the extraordinary delay, and upheld the Commissioner (Appeals)' decision to dismiss the appeal for being time-barred under Section 85(3A) of the Finance Act, 1994.