Windmill commissioning evidence supported higher depreciation where grid connection and electricity generation proved operational use before the relev...
Pharmaceutical promotion and transfer-pricing comparability principles limited disallowances, while uncorroborated search allegations and unsupported ...
Business expenditure substantiation supports scrap credits, statutory payments and expense claims, while depreciation requires proof of actual busines...
The High Court quashed and set aside the Tribunal's order which had refused to condone the delay of 2208 days in filing the appeal. The High Court held that the Tribunal's finding that the order was delivered at the address mentioned in Form No. 35 was perverse and contrary to the record. The delay of 2208 days in preferring the appeal was condoned by the High Court, and the matter was remanded back to the Tribunal to be decided on merits.
The High Court quashed and set aside the Tribunal's order which had refused to condone the delay of 2208 days in filing the appeal. The High Court held that the Tribunal's finding that the order was delivered at the address mentioned in Form No. 35 was perverse and contrary to the record. The delay of 2208 days in preferring the appeal was condoned by the High Court, and the matter was remanded back to the Tribunal to be decided on merits.