Clean slate principle extinguishes uncrystallised operational claims and bars continuation of pending recovery and arbitral proceedings after plan app...
Works contract classification governs composite layout-development contracts where VAT-paid goods are transferred alongside construction and infrastru...
Specified income tax exemption for pollution control body remains conditional on non-commercial activity, unchanged income character, and return filin...
Jurisdictional facts in certificate-of-origin discrepancies can support customs show-cause proceedings, leaving factual explanations for departmental ...
Page of 4800
Press 'Enter' after typing page number.
1021 to 1040 of 95999 Results
❮
❯
❯❯
0 / 200
Expand Note
Add to Folder
No Folders have been created
+
Are you sure you want to delete "My most important" ?
The Delhi High Court set aside an order demanding payment including penalty u/s 73 of the CGST Act, 2017 due to the petitioner's lack of awareness and inability to respond to the proceedings, violating natural justice principles. The court found that the petitioner missed the notice uploaded in the "Additional Notices" tab on the portal. The impugned order was overturned, granting the petitioner an opportunity to respond to the Show Cause Notice and directing the respondent to reopen the portal for a response within four weeks. The petition was disposed of.
The Delhi High Court set aside an order demanding payment including penalty u/s 73 of the CGST Act, 2017 due to the petitioner's lack of awareness and inability to respond to the proceedings, violating natural justice principles. The court found that the petitioner missed the notice uploaded in the "Additional Notices" tab on the portal. The impugned order was overturned, granting the petitioner an opportunity to respond to the Show Cause Notice and directing the respondent to reopen the portal for a response within four weeks. The petition was disposed of.