Arrest safeguards and transit remand requirements invalidated detention following inter-State transfer without communicated grounds or magistrate auth...
Arrest safeguards require disclosed grounds, relative intimation and transit remand, while duplicate prosecution under the CGST framework is unsustain...
Document Identification Number defects can invalidate GST assessments, with delayed challenges entertained conditionally where patent irregularities e...
Windmill commissioning evidence supported higher depreciation where grid connection and electricity generation proved operational use before the relev...
Rectification u/s 154 - period of limitation - original order passed by the AO dated 05/04/2011 - AO has already passed a suo-moto rectification order u/s 154 dated 18/03/2014 - Even though the surcharge was levied in terms of the first order, the order so sought to be rectified by the assessee is the rectified order dated 18/03/2014 wherein the surcharge continued to be levied on the assessee besides additional interest. Therefore, the rectification application dated 01/07/2016 is well within the limitation period as so prescribed and is not barred by limitation. - AT
Rectification u/s 154 - period of limitation - original order passed by the AO dated 05/04/2011 - AO has already passed a suo-moto rectification order u/s 154 dated 18/03/2014 - Even though the surcharge was levied in terms of the first order, the order so sought to be rectified by the assessee is the rectified order dated 18/03/2014 wherein the surcharge continued to be levied on the assessee besides additional interest. Therefore, the rectification application dated 01/07/2016 is well within the limitation period as so prescribed and is not barred by limitation. - AT
Note: It is a system-generated summary and is for quick reference only.