Arrest safeguards and transit remand requirements invalidated detention following inter-State transfer without communicated grounds or magistrate auth...
Arrest safeguards require disclosed grounds, relative intimation and transit remand, while duplicate prosecution under the CGST framework is unsustain...
Document Identification Number defects can invalidate GST assessments, with delayed challenges entertained conditionally where patent irregularities e...
Windmill commissioning evidence supported higher depreciation where grid connection and electricity generation proved operational use before the relev...
Pharmaceutical promotion and transfer-pricing comparability principles limited disallowances, while uncorroborated search allegations and unsupported ...
Business expenditure substantiation supports scrap credits, statutory payments and expense claims, while depreciation requires proof of actual busines...
Insolvency and BankruptcySeptember 12, 2020Case LawsTri
Approval of Resolution Plan - CIRP process - dissenting financial creditors - No financial creditor either assenting or dissenting can challenge a Resolution Plan, as approved by the CoC, even before the Adjudicating Authority approve the said Plan on the ground that the Plan does not meet the requirements of Section 30 (2) of the Code. Hence, there is no need to examine the rival submissions on this issue at this stage. - Tri
Approval of Resolution Plan - CIRP process - dissenting financial creditors - No financial creditor either assenting or dissenting can challenge a Resolution Plan, as approved by the CoC, even before the Adjudicating Authority approve the said Plan on the ground that the Plan does not meet the requirements of Section 30 (2) of the Code. Hence, there is no need to examine the rival submissions on this issue at this stage. - Tri