The contract for Erection, Procurement and Commissioning of Solar Power Plant falls under the ambit “Works Contract Services” (SAC 9954) and attracts 18% rate of tax under IGST Act, or 9% each under the CGST and SGST Acts.
The contract for Erection, Procurement and Commissioning of Solar Power Plant falls under the ambit “Works Contract Services” (SAC 9954) and attracts 18% rate of tax under IGST Act, or 9% each under the CGST and SGST Acts.