Composite inpatient healthcare supply may retain exemption despite MRP medicine billing, while separate taxable sale characterisation remains disputed...
Working-capital adjustment determines whether software-services transfer-pricing margins fall within the statutory tolerance range, eliminating any ad...
Permanent establishment deductions upheld for expatriate salaries, direct costs and trading losses, while head-office costs require fresh classificati...
Clean slate principle bars revival of pre-CIRP electricity dues and the connected late payment surcharge after approval of a resolution plan. Where the surcharge had already arisen on unpaid electricity charges before CIRP, extinguishment of the principal pre-resolution claim also prevents indirect recovery of the related surcharge as a condition for restoring supply. Reliance on post-disconnection billing or section 56(2) concepts was misplaced because the liability had already been billed and formed part of the pre-CIRP dues. A demand for pre-CIRP surcharge as a precondition to a fresh electricity connection was therefore treated as arbitrary and without authority of law.
Clean slate principle bars revival of pre-CIRP electricity dues and the connected late payment surcharge after approval of a resolution plan. Where the surcharge had already arisen on unpaid electricity charges before CIRP, extinguishment of the principal pre-resolution claim also prevents indirect recovery of the related surcharge as a condition for restoring supply. Reliance on post-disconnection billing or section 56(2) concepts was misplaced because the liability had already been billed and formed part of the pre-CIRP dues. A demand for pre-CIRP surcharge as a precondition to a fresh electricity connection was therefore treated as arbitrary and without authority of law.
Note: It is a system-generated summary and is for quick reference only.