Opportunity to respond to jurisdictional reports is mandatory before customs settlement duty enhancement; connected applications require consistent ad...
Specific customs headings for scaffolding components prevail over general classification, invalidating misclassification proceedings and enabling with...
Liquidator appointment under Section 34 requires consideration of creditor recommendations, valid professional authorisation, and preservation of vali...
Income-tax exemption for specified regulatory fees and government grants applies subject to non-commercial activity and continuing compliance conditio...
Digital accessibility audit and remediation deadlines extended, while all other disability-compliance obligations for regulated entities remain unchan...
Page of 4803
Press 'Enter' after typing page number.
621 to 640 of 96047 Results
❮
❯
❯❯
0 / 200
Expand Note
Add to Folder
No Folders have been created
+
Are you sure you want to delete "My most important" ?
Composite EPC/turnkey public utility construction contracts for Government agencies were held not to be Consulting Engineer's service because the agreements showed complete construction, procurement, labour, commissioning, quality and maintenance obligations, with the fee representing only the contractor's profit margin. The Revenue could not vivisect the contract and tax only the fee component under that head, so the demand failed on classification. The extended period was also inapplicable because the projects were treated as exempt public utility works, the assessee acted under bona fide belief, and there was no specific evidence of wilful suppression or intent to evade.
Composite EPC/turnkey public utility construction contracts for Government agencies were held not to be Consulting Engineer's service because the agreements showed complete construction, procurement, labour, commissioning, quality and maintenance obligations, with the fee representing only the contractor's profit margin. The Revenue could not vivisect the contract and tax only the fee component under that head, so the demand failed on classification. The extended period was also inapplicable because the projects were treated as exempt public utility works, the assessee acted under bona fide belief, and there was no specific evidence of wilful suppression or intent to evade.