Just a moment...
Press 'Enter' to add multiple search terms. Rules for Better Search
Use comma for multiple locations.
---------------- For section wise search only -----------------
Accuracy Level ~ 90%
Press 'Enter' after typing page number.
Press 'Enter' after typing page number.
No Folders have been created
Are you sure you want to delete "My most important" ?
NOTE:
Press 'Enter' after typing page number.
Press 'Enter' after typing page number.
Don't have an account? Register Here
Press 'Enter' after typing page number.
Issues: Whether the High Court was justified in setting aside the arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996 and in restoring the deduction of liquidated damages for delayed performance of the construction contract.
Analysis: The arbitral tribunal had examined the contractual clauses governing liquidated damages, extension of time, and the consequences of delay, and had found that the contractor failed to complete the work within the extended period while the employer had repeatedly reserved its right to levy liquidated damages. The Court reiterated that Section 34 of the Arbitration and Conciliation Act, 1996 permits interference only on the limited grounds specified in that provision and does not authorise a reappreciation of evidence or substitution of another possible interpretation of the contract. The view taken by the arbitral tribunal was held to be a plausible view on the material before it. The learned Single Judge had exceeded the limited jurisdiction under Section 34 by re-evaluating the contractual effect of extension of time and by setting aside the award on grounds outside the statutory parameters.
Conclusion: The High Court's Division Bench was correct in restoring the arbitral award, and the challenge to the deduction of liquidated damages failed.