Just a moment...

Top
Help
×

By creating an account you can:

Logo TaxTMI
>
Call Us / Help / Feedback

Contact Us At :

E-mail: [email protected]

Call / WhatsApp at: +91 99117 96707

For more information, Check Contact Us

FAQs :

To know Frequently Asked Questions, Check FAQs

Most Asked Video Tutorials :

For more tutorials, Check Video Tutorials

Submit Feedback/Suggestion :

Email :
Please provide your email address so we can follow up on your feedback.
Category :
Description :
Min 15 characters0/2000
TMI Blog
Home / RSS

2024 (11) TMI 1509

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....al (hereafter the Arbitral Tribunal) comprising of a Sole Arbitrator. 2. The impugned award was rendered in the context of disputes that had arisen between the parties in connection with an agreement dated 11.01.2007 for designing, supplying, installation, testing and commissioning of high mast signage systems of various heights and types at various IOCL retail outlets in the State of Tamil Nadu and Union Territory of Pondicherry (hereafter referred to as the Work Order). 3. Fiberfill had made five claims, which were the subject matter of arbitration before the Arbitral Tribunal. The same included a claim of Rs.22,08,528/- being an amount that was deducted by IOCL towards price adjustment from the bills raised by Fiberfill for the work done; interest at the rate of 18% on the sum of Rs.22,08,528/- from the date the amounts were withheld by IOCL till the actual date of release; Rs.75,50,000/- towards Escalation; Rs.1,50,00,000/- towards Loss of Business Opportunity; and Rs.80,00,640/- towards Manpower Retention. The Arbitral Tribunal rejected all the aforesaid claims and found that Fiberfill is not entitled to any relief. 4. During the course of proceedings relating to Fiberfill'....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....dian Partnership Act, 1932. It is primarily engaged in the business of steel fabrication and executing civil and electrical engineering contracts. 9. The bid documents included the SIT, which inter alia, stated the procedure for awarding the contract. It was expressly provided that the SIT and the bid documents would form an integral part of the Contract. Clause 8.0 of the SIT provided that the "the Rate Contract shall be valid for a period of One year from the date of its finalization and shall not be extendable for a further period of one year with mutual consent" [Clause 8 of the SIT]. 10. It was expressly provided that the finalization of the contract would not entail any right to the contractors for securing the work orders from IOCL. The SIT further stated that IOCL intended to shortlist two contractors and to award 60% of the total value of work to the tenderer quoting the lowest acceptable rate (L-1) and balance 40% of the work to a contractor offering the next lowest rate (L-2). 11. Clause 9 of the SIT expressly provided that the work was required to be completed in all respects within a period of twelve weeks from the date of issuance of "Call up Order". 12. Clause 9....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....rders - as noted above, IOCL had issued six Call up Orders after the initial term of the Contract had expired - there was also a delay in installation of the high mast signages for various reasons. 17. According to IOCL, the delay in execution of installation of the high mast signages exceeded the period of sixty days as extended by the period of delay on account of justifiable reasons or those that were not attributable to Fiberfill. IOCL, thus, withheld an amount of Rs.22,08,528/- from the amounts payable to Fiberfill. IOCL claimed that the said deductions were made in accordance with Clause 4.4.0.0 of the GCC and Clause 9 of the SIT. A tabular statement setting out the period of delay on account of which IOCL withheld the payments is set out below: CALL UP ORDER NO. DATE, BY WHICH, THE RESPONDENT WAS TO COMPLETE WORKS DATE, BY WHICH, THE RESPONDENT HAD ACTUALLY COMPLETED WORKS NO. OF DAYS, BY WHICH, WORK HAS BEEN DELAYED 2nd 11.02.2008 16.09.2008 217 days 6th 04.08.2008 10.11.2008 98 days 8th 01.12.2008 03.07.2009 210 days 9th 13.03.2009 01.04.2011 More than 730 days 11th 24.06.2009 12.07.2010 More than 365 days 12th 11.11.2009 15.05.2011 More than 1....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....educted on account of liquidated damages/Penalty: The Claimant is entitled to Rs. 22,08,528/- deducted from the bills on account of Liquidated damages/penalty alongwith interest @ 18% p.a. from the date the amounts have been withheld i.e. 01.05.2008 till 31.12.2014 amounting to Rs. 26,59,917/- II). Claim due to delay damages. i) Escalation Amount (On material, transportation, execution cost etc) aggregating to Rs. 75,50,000/-. ii) Loss of Business Opportunity aggregating to Rs. 1,50,00,000/-. iii) Manpower recruitment cost over a period of 4 year @Rs.20 Lacs p.a aggregating to Rs. 80,00,640/-, the break-up is provided below: a) Engineers for 48 Months @Rs.65,000/- per month Rs.31,20,000/- b) 3 Nos. Supervisor for 48 Months @Rs.28,000/- per month Rs.40,32,000/- c) Mason & Labour Cost Rs.8,48,640/-" 25. IOCL countered the aforesaid claims by filing its written statement of defence. 26. The arbitral proceedings culminated in the impugned award whereby the claims made by Fiberfill were rejected. 27. Fiberfill filed a petition assailing the impugned award under Section 34 of the A&C Act, which was partly allowed in terms of the impugned order. REASONS AND CONCLUSIO....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....ed to Fiberfill's Claim nos.1 and 2 - Fiberfill's claim for amount of Rs.22,08,528/-, which was deducted by IOCL from its bills, and interest at the rate of 18% per annum on the said amount. 31. It was contended on behalf of IOCL that the learned Single Judge had erred in proceeding on the basis that IOCL was required to establish that it had suffered any loss for sustaining a deduction of the aforesaid amount from the bills raised by Fiberfill. It was submitted that the said deduction was in accordance with Clause 9 of the SIT and Clause 4.4.2.0 of the GCC and the learned Single Judge had erred in proceeding on the basis that Clause 4.4.2.0 of the GCC provides for liquidated damages while ignoring Clause 4.4.2.2 of the GCC, which expressly provided that the provisions of the said Clause 4.4.2.0 of the GCC were not to be understood or construed as liquidated damages or penalty under Section 74 of the Indian Contract Act, 1872. It was further contended that even if the price adjustment clause was to be read as providing for levy of liquidated damages on account of delay in setting up of the high mast signages, there is an inherent presumption that IOCL would have suffered a loss on....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....h as it provided for compensation even if there was a delay in execution of a single signage tower. 36. The Arbitral Tribunal found that out of twelve Call up Orders placed by IOCL, work pertaining to six Call up Orders were inordinately delayed. IOCL had, thus, recovered compensation only in respect of six Call up Orders. The Arbitral Tribunal noted that IOCL had granted time extensions to Fiberfill whenever the same was considered justifiable. However, extension of time on account of various reasons including late appointment of the TPI Agency or excessive rains etc. could not be construed as waiver of the contractual clause, which specifically provided that the time was the essence of the contract. 37. The learned Single Judge has declined to interfere with either of the two aforesaid findings given the limited scope of examination under Section 34 of the A&C Act. We concur with the said view. The findings of the Arbitral Tribunal that there was delay on the part of Fiberfill in executing six Call up Orders, and that the time was the essence of the Contract, did not warrant any interference in proceedings under Section 34 of the A&C Act. 38. The only question to be examined i....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....r Mechanical Completion of the Unit(s) final completion of the works achieved within 8 (eight) weeks of the starting date for discount calculation -4% of the total contract value. (ix) For Mechanical Completion of the Unit(s)/ final completion of the works achieved within 9 (Nine) weeks of the starting date for discount calculation-4 ½ % of the total contract value. (x) For Mechanical Completion of the Unit(s)/ final completion of the works achieved within 10 (ten) weeks of the starting date for discount calculation 5% of the total contract value. (xi) For Mechanical Completion of the Unit(s)/ final completion of the works achieved within 11 (eleven) weeks of the starting date for discount calculation - 5 ½ % of the total contract value. (xii) For Mechanical Completion of the Unit(s)/ final completion of the works achieved within 12 (twelve) weeks of the starting date for discount calculation-6 ½ % of the total contract value. (xiii) For Mechanical Completion of the Unit(s)/ final completion of the works achieved within 13 (thirteen) weeks of the starting date for discount calculation 6 ½ % of the total contract value. (xiv) For Mechanical Co....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....use 4.4.2.0 above shall prevent the OWNER from exercising its right of termination of Contract under Clause 7.0.1.0 hereof and associated clauses thereunder, and OWNER shall be entitled, in the event of exercising its said right of termination after the last date for Mechanical Completion of the Unit(s) and/or final completion of the works as stipulated in the relative Progress Schedule without prejudice to any other right or remedy available to the OWNER, to discount as aforesaid in the contractual price of services in addition to any amount as may be due consequent to a termination under Clause 7.0.1.0 hereof and associated clauses there under." "9.0 WORKING TIME AND COMPLETION PERIOD: The work entrusted in each call up order shall be completed in all respect within 12 (Twelve) weeks from the date of issuance of Call Up order. 9.1 The contractor shall have to carry out the works during the normal working hours of the Corporation. However, with the concurrence of the location/site in charge the contractor may be permitted to work beyond the normal working hours and the expenses if any shall be borne by the contractor. 9.2 The entire work must be completed within the stipulat....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....ven though the Clauses 4.4.0.0, 4.4.1.0, 4.4.2.0 of Section 3 of the General Conditions of Contract state that the Respondent can adjust price for delay in completion, the deduction of the amount payable to the Claimant on account the purported delay is in essence a penalty/liquidated damaged imposed on the Claimant, which is impermissible under the law. The said Clauses are harsh, penal in nature and unenforceable inasmuch as the penalty imposed is a percentage of the total contract value even for a delay in mechanical completion of one unit of the work order." 40. IOCL countered the said assertion. It denied that the Clause 4.4.2.0 of the GCC read with Clause 9.0 of the SIT was in the nature of imposing a penalty or that the liquidated damages imposed by IOCL were impermissible. IOCL claimed that it was "permissible in law that contracting parties can pre-estimate the damages and arising out of any breach and quantify the same including delay and such pre-estimation of damages is legally valid and enforceable". The said averment is suggestive of IOCL's stand that the clause 4.4.2.0 of the GCC provides for a genuine pre-estimate of loss that IOCL would suffer if there was a delay....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....m, being in line with Clause 4.4.0.0 of the GCC and Clause 9 of Special Instructions to Tenderers/Contractors were contractual and valid. The argument of the Claimants as to that "the amount deducted by the respondent is by way of penalty and not compensation, since the Respondent makes no claim for loss or injury" is not acceptable in as much as the deductions were made by Respondents strictly in line with terms and conditions of the contract." 46. It is also important to note that there is no finding of the Arbitral Tribunal to the effect that Clause 4.4.2.0 of the GCC embodies a measure for genuine pre-estimate of damages on account of delay - a case that was canvassed on behalf of IOCL before us as well. 47. Concededly, IOCL had made no averment in its written statement claiming that it had suffered any loss. The contention advanced that such loss was obvious as the customers and the staff of IOCL would be inconvenienced by the area being dug off or cordoned off, does not appear to have been made before the Arbitral Tribunal. In any view, the Arbitral Tribunal has not returned any finding on any such contention. It is also important to note that Fiberfill contests the said ....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....ch proof is not dispensed with. It is only in cases where damage or loss is difficult or impossible to prove that the liquidated amount named in the contract, if a genuine pre-estimate of damage or loss, can be awarded. 43.7. Section 74 will apply to cases of forfeiture of earnest money under a contract. Where, however, forfeiture takes place under the terms and conditions of a public auction before agreement is reached, Section 74 would have no application." [emphasis supplied] 49. In Mahanagar Telephone Nigam Ltd. v. Finolex Cables Limited, 2017 SCC OnLine Del 10497, a Division Bench of this Court had considered a case where damages had been imposed on account of delay in the delivery of stores. The levy of compensation on account of delay was more or less in similar terms as contemplated under the GCC as applicable to the Work Order in this case. The contractual clause as considered by the court in the aforesaid case is set out below: "17. Liquidated Damages 17.1 The date of delivery of the stores stipulated in the acceptance of Purchase Order should be deemed to be the essence of the contract and delivery must be completed not later than the dates specified therein. Ext....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....the contract was of such nature that it was not possible to evaluate the damages and therefore, that 10% of the amount quantified in the contract between the parties as liquidated damages had to be treated as being reasonable award of damages. 48. It is clearly stated in para 43.6 of Kailash Nath that in case where damages are difficult or impossible to prove, the claimants would be entitled to the liquidated damages if they were a genuine pre-estimate of the damage. No material at all in this regard was produced before the arbitral award. MTNL has not even asserted that it had suffered loss." 51. Before concluding, we must add that in a given case where contractual terms provide for a variable consideration depending on the performance of the agreement, the said term is required to be enforced. It is not necessary that in all cases where the parties have agreed to reduction in consideration on the basis of performance, that the contractual term to that effect is to be construed as the clause for damages. In such cases, the contractual clause must be read as an integral part of the rights and obligations of the parties, which are required to be performed. Clause 4.2.2.2 of the ....