Just a moment...

Report
FeedbackReport
Bars
Logo TaxTMI
>
×

By creating an account you can:

Feedback/Report an Error
Email :
Please provide your email address so we can follow up on your feedback.
Category :
Description :
Min 15 characters0/2000
TMI Blog
Home / RSS

2023 (11) TMI 493

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

.... the rate of 7.25 % from the date of the Award till final payment and/or realization. 3. Further by the impugned order dated 20.07.2020 the Arbitral Tribunal has decided preliminary issue "whether the dispute involves allegations of serious fraud by the Claimant thereby rendered the dispute non-arbitrable?" against the Petitioner herein. Thus, the Arbitral Tribunal held that at the higher the allegation in the statement of Defence is a case of simple fraud and not a case of serious allegations of fraud thus held that the claims are arbitrable. 4. By an order dated 01.01.2022 passed by this Court in the above Commercial Arbitration Petition, this Court was of the opinion that the Commercial Arbitration Petition can be heard and disposed of at the admission stage. This was whilst considering the application of the Respondent herein for withdrawal of the awarded amount deposited by the Petitioner in this Court pursuant to the order dated 16.12.2021. Accordingly, directions were issued to the Counsel for the parties for placing on record brief written notes of arguments and compilation of judgments if any, within a period of four weeks from the date of the said order. Thereafter a fu....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....he Chandrapur TPS on 30.09.2013. viii) A Circular No. 41/2013 was issued on 21.10.2013 by which importers of coal from ASEAN countries could pay for the first time a total duty of 2% i.e. 0% BCD + 2% CVD (instead of 6% CVD). ix) The Contract for supply of 9,56,500 MT to Chandrapur TPS was executed on 25.10.2013 whereunder Contract period began on 13.09.2013. x) The Petitioner released on 04.12.2013 the 1st payment (90% through LC) for invoice submitted by the Respondent for Bhusawal TPS. The payment included the BCD component. xi) The Petitioner released the 1st payment (90% through LC) for invoice submitted by the Respondent for Chandrapur TPS on 31.12.2013. This payment included the BCD component. xii) The Petitioner addressed a letter on 01.03.2014 to the Respondent raising the issue of availing concessional BCD. By this time, approximately 47.44% of the final quantity was supplied to Bhusawal TPS and 38% of the final quantity was supplied to Chandrapur TPS. xiii) The Respondent replied to the Petitioner's letter dated 01.03.2014 by their letter dated 14.03.2014 disputing the contents thereof and on the grounds that (a) the contracts prevailing customs duty ....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....e. xxiii) This was responded to by the Respondent vide letter dated 13.10.2014 protesting against the decision taken by the Petitioner in letter dated 09.10.2014. The Respondent issued final invoice for the full MIR quantity. xxiv) The PBG for Bhusawal TPS was discharged on 31.10.2014 and the PBG for Chandrapur TPS was discharged on 01.11.2014. xxv) The Petitioner addressed a letter to the Respondent on 28.11.2014 alleging that the tolerance/variation of +/- 2% was applicable separately for supplies made to Chandrapur TPS and Khaparkheda TPS. xxvi) The Respondent addressed several letters to the Petitioner for releasing balance payments which were outstanding against the contracts. xxvii) The Respondent addressed a letter to the Petitioner on 22.01.2015 requesting it to accept the quantity tolerance for supplies made under the Chandrapur Contract TPS and accept the final invoice. xxviii) On 31.03.2015, the Petitioner made part payment of Rs. 34,31,00,903/- to the Respondent after delay of more than 12 months from due date of payment. xxix) The Respondent by letter dated 08.05.2015 requested the Petitioner for the deductions towards BCD to be released. xxx) T....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....Revenue Intelligence (DRI) had investigated the supply of coal by the Claimant to the Respondent/ Petitioner herein and the DRI had found that the Claimant has perpetrated fraud and misrepresentation in importing and supplying the said coal. The Order of DRI was set aside by CESTAT. The Appeal from the said order by CESTAT was thereafter dismissed by this Court. xli) The impugned order dated 20.07.2020 was passed dismissing the preliminary objection raised of disputes being non-arbitrable on account of serious fraud allegedly committed by the Respondent. xlii) The impugned Award was passed on 21.04.2021 directing the Petitioner to pay the Respondent a sum of Rs. 22,06,47,321/- alongwith interest @7.25% p.a. from the Award date till payment. xliii) On 20.08.2021, the present Commercial Arbitration Petition was filed. xliv) The Civil Appeal against this Court's Order on DRI findings in the Supreme Court was withdrawn on 24.01.2023 6. Mr. Pankaj Sawant, learned Senior Counsel appearing for the Petitioner has made submissions on the Issue No. 1 which is with regard to the recoveries of 2% BDC. He has submitted that the Arbitral Tribunal has erroneously held that reliance ....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....er, there is no evidence to suggest that obtaining Forms A-1 would have cost more than 2% BCD exemption that was not claimed. 10. Mr. Sawant has submitted that as per Clause 10 of Annexure III of the ASEAN Notification, an AIFTA certificate of origin could even be obtained retroactively in exceptional cases and no longer than 12 months from the date of shipment. He has submitted that the Claimant could have availed the benefit of this provision by making an application for the AIFTA certificate for the remaining goods to be shipped after the enforcement of the Notification No. 41/2013. 11. Mr. Sawant has submitted that the Claimant did not produce any evidence to suggest that they had ever applied for the AIFTA certificate of origin. Therefore, this clearly indicates the approach of the Claimant, thereby, causing further loss of public money. 12. Mr. Sawant has submitted that the Arbitral Tribunal ought to have taken into consideration the fact that a concession of BCD having become available (in practical terms), then it was an obligation on the part of the Claimant under Clause 5.2 to avail of such concession, which the Claimant failed to do so. He has submitted that on the ba....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....h the task of construction with too nice a concentration on individual words. The mercantile contract should be construed in a business fashion and in a manner that would make good commercial sense. He has placed reliance upon Chitty on Contracts, 27th Edn., Vol. I 1994, and in particular paragraph 45 regarding contracts in standard form and paragraph 12.013 regarding onerous or unusual terms. He has also referred to paragraph 12.040 regarding intention of parties wherein the Author has commented that one must consider the meaning of the words used, not what one may guess to be the intention of parties. Further, the law does not approach the task of construction with too nice a concentration on individual words with regard to dealing with mercantile Contracts, the author has stated that the commercial documents 'must be constructed in a business fashion' and 'there must be ascribed to the words a meaning that would make good commercial sense'. 17. Mr. Sawant has also placed reliance upon the decision of the Supreme Court in Rajasthan State Industrial Development and Investment Corporation vs. Diamond and Gem Development Corporation Ltd. 2013 (5) SCC 470 wherein the Supreme Court h....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....Ansari; and iv) State of Gujarat v. Amber Builders, (2 Judges) paras 19 to 21 - holds that Gangotri Enterprises is per incuriam because it relies upon Raman Iron Foundry which has been specifically over-ruled by a 3-Judge Bench in H.M. Kamaluddin Ansari. 20. Mr. Sawant has submitted that the Petitioner being a Public Sector Undertaking is considered a State according to Article 12 of the Constitution of India. As the funds involved in the contracts in question are public money, the terms of the contracts have been designated to protect the public interest and ensure that the work is carried out with care and diligence. 21. Mr. Sawant has thereafter made submissions with regard issues Nos. 2 to 5 being beyond the scope of reference. He has submitted that the Claimant's entitlement is limited to Claim No. 1, as per the High Court's order dated 30.10.2018. Moreover, the Counsel representing the Claimant made a clear statement that the Claimant's claim is restricted to the 2% difference that had been deducted by the Petitioner. He has referred to the statement made by the Counsel on behalf of the Claimant's recorded in the said order. He has submitted that the statement was made ....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....o. 2, which states that "The seller shall note that if any excess quantity beyond contractual quantity considering tolerance of +2% is received at the TPS: the payment for such quantity shall not be made". He has submitted that the Arbitral Tribunal ought to have considered that clause 8.7 of Schedule-A is an express prohibition in the contract and that if the claim is granted then the same will be contrary to the express prohibition in the contract. He has submitted that on the same principles of 'business-like interpretation', 'common sense interpretation' and 'purposive interpretation' of the contract (as per the supreme Court decisions already quoted above), it is clear that the tolerance levels of +/- 2% is to be applied separately qua each TPS. 25. Mr. Sawant has submitted that if the Claimant's argument on interpretation of clauses 8.7 and 8.11 is to be accepted, then it would lead to an absurd situation viz. that the Claimant would be free to deliver the entire quantity at the original TPS location (and zero quantity at the new TPS location) and still claim that there is no excess delivery at all. Such hyper-technical interpretation not only renders clause 8.7 useless and ....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....e Arbitral Tribunal has erred in holding that liquidated damages has not been proved by leading evidence. 29. Mr. Sawant has made submissions with regard to Issue No. 4 - short payment under Contract No. 2041 dated 30.08.2023. He has submitted that reconciliation proceedings are not yet concluded as the Claimant have made various alterations in view of the disputed amount which is yet to be identified. The Respondent denies that an amount of Rs. 21,76,555/- is due and payable under the Bhusawal Contract. 30. Mr. Sawant has in respect of Issue No. 7 - Limitation, submitted that the cause of action first arose on 19.03.2014, when the Petitioner informed the Claimant that the Petitioner would be recovering the said amounts from the payments against the Contract. Therefore, on the basis of the same, the Arbitration reference commenced by arbitration notice dated 31.08.2017 which is barred by Limitation and therefore on this ground also all the claims of the Claimant needs to be set aside. He has submitted that alternatively, all deductions/recoveries made three years prior to the date when the arbitration notice dated 31.08.2017 was received by the Respondent are clearly barred by li....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....mitted that the Petitioner's challenge to the impugned Award and interim order are based on the premise that the Arbitral Tribunal had incorrectly interpreted the terms of the Supply Contracts. He has submitted that there are a plethora of judgments which have defined the limited contours or the restricted remit of a Court when a Petition is adjudicated under Section 34 of the Arbitration and Conciliation Act, 1996 (Arbitration Act). Regarding the question of interpretation of contracts, it is settled law that the Arbitrator is empowered to interpret the contract. This means that no Court can interpret the contract for the Arbitrator. The interpretation and construction of a contract is therefore primarily for the Arbitrator to decide. 36. Mr. Nankani has submitted that there is no ground made out by the Petitioner of patent illegality. The Award is not against public policy. The Award is also not perverse. The Award is a reasoned speaking award. He has submitted that the Arbitral Tribunal is a sole master of the quality and quantity of evidence and the view taken by the Arbitral Tribunal is the correct view. He has submitted that where there are two views possible, if the view pr....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

.... in Jayant Dalal vs. Commissioner (1997) 10 SCC 402 that the said Circular is binding only on the Department and not on the Assessee. Being clarificatory in nature, the same only confirms the law as it existed at the onset. 40 Mr. Nankani has submitted at the beginning of the contractual period, coal attracted 3 rates of basic customs duty. 10% as per Customs Tariff, 2% as per Notification 12/2013 Cus. and Nil as per Notification 46/2011 as amended on 31.12.2012. There was no change in the rate of BCD after the contractual period started to run. Hence, Clause 5.2 of the Contract is not attracted. The parties chose to apply the concessional rate of the basic customs duty @ 2%. There has been no change in the rate of BCD during the contractual period. He has submitted that the parties chose not to lead oral evidence. Having chosen not to lead oral evidence, the Petitioner cannot reply upon or call back the said Circular dated 03.10.2013 which was not in existence on the date of execution of the contract. 41. Mr. Nankani has submitted that the Petitioner has made submissions on the contract requiring to be interpreted in a business-like, purposive and common-sense manner. He has sub....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

.... apply for the Form A-1 pre-shipment, it was not possible to make this happen midway. 45. Mr. Nankani has addressed the other issue raised by Mr. Sawant during arguments and which relates to Claim Nos. 2 to 5 being beyond the scope of reference. He has submitted that the Arbitral Tribunal has correctly interpreted that Section 11 of the Arbitration Act does not require the Chief Justice or his designate to identify the disputes or refer them to the Arbitral Tribunal for adjudication. Hence, the order dated 30.10.2018 passed in the Section 11 Application referring the disputes to arbitration could not have restricted the Respondent from making its claims as per its notice of invocation dated 31.08.2017. The operative part of the said order dated 30th October, 2018 did not exclude any claims. The Arbitral Tribunal has also appreciated that since the Chief Engineer (FMC) had already rejected the Respondent's Claim Nos. 2 and 3, there could be no question of the Respondent again going to the same authority for adjudication of these claims. With regard to Claim No. 4, the Arbitral Tribunal has found that there was no dispute as to the reconciliation sheet jointly signed by the parties ....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....on-performance of the entire contract or part thereof and that the Petitioner was entitled to deduct liquidated damages under Clause 15.1 of the Chandrapur Contract. He has submitted that this calculation of +/-2% with reference to 80,000 MT is erroneous. The tolerance limit of +/-2% had to be calculated on the total quantity of 9,56,500 as per the Chandrapur Contract. The tolerance limit cannot independently or on stand-alone basis, be applied to diverted quantity of 80,000 MT since it is part of the ordered quantity under the Chandrapur Contract. There is undisputedly no separate contract for 80,000 MT diverted to Khaparkheda. He has accordingly submitted that there is no merit to the challenge of the Petitioner to the Arbitral Award on this issue. 49. Mr. Nankani has thereafter addressed the issue of liquidated damages. He has submitted that the Arbitral Tribunal has held that since there was no shortfall more than permissible limits under the Supply Contracts, the deductions effected by the Petitioner by way of Liquidated Damages were impermissible. The Arbitral Tribunal had noted that it was for the Petitioner to prove damages suffered. However no evidence was produced in thi....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....wal Contract and on 22.03.2017 in relation to Chandrapur Contract. Hence, the Arbitral Tribunal has rightly held that the claims of the Respondent were within limitation. 52. Mr. Nankani has submitted that the notice of arbitration is dated 31.08.2017 and in view of part payments made by the Petitioner to the Respondent between October and November, 2015, these factors have been rightly taken into consideration by the Arbitral Tribunal including as aforementioned the Joint Reconciliation of Accounts completed by the parties on 24.05.2017 in case of Bhusawal Contract and on 22.03.2017 in respect of the Chandrapur Contract in which the amounts deducted (and now claimed) were also finalized and net amount post adjustments payable to the Respondent have been mentioned. Further, the Petitioner has accepted the Respondent's claim No. 4 i.e. short payment under BTPS Contract for Rs. 21,76,555/- and paid the same to the Respondent on 26.08.2021. Hence, there is no merit in the challenge to the Arbitral Award on the issue of limitation. 53. Mr. Nankani has accordingly submitted that there is no valid ground of challenge under Section 34 of the Arbitration Act in the present Petition and a....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....tract and the Court cannot interpret contracts for the Arbitrator. The interpretation and construction of a contract is primarily for the Arbitrator. The Arbitrator's view on the interpretation of the Clauses of the contract, is a possible view and hence calls for no interference under Section 34 of the Arbitration and Conciliation Act, 1996. Thus, in my view there is no merit in the challenge to the finding of the Arbitral Tribunal with regard to issue No. 1. The Arbitral Tribunal having interpreted the aforementioned clauses which this Court finds is a possible interpretation cannot be a ground of challenge under Section 34 of the Arbitration Act. 57. The decisions of the Supreme Court relied upon by the Respondent namely Ssangyong Engineering & Construction Co. Ltd. (supra); Delhi Airport Metro Express Pvt. Ltd. (supra) and UHL Power Company Ltd. (supra) are apposite. 58. With regard to the Petitioner's contention of Issue Nos. 2 to 5 being beyond this Court's reference and thus, not arbitrable, I do not find any merit in this contention. This is in view of the order dated 30.10.2018 not placing any restriction upon the Respondent making its claims as per Notice of Invocation ....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

.... +/ -2% was against contracted quantity if fully ordered or against the ordered quantity. The parties were required to follow the procedure under Clause 35 of the Contract and no independent contract was entered into between the parties for the purpose of diversion of quantity. 61. The Arbitral Tribunal in my view has correctly accepted the contention of the Respondent that the tolerance limit of +/- 2% under Clause 8.7 of the contract cannot independently or on stand alone be applied to the diverted quantity of 80,000 MT since it is a part of the ordered quantity and the tolerance limit of +/-2% necessarily would have to be calculated on the total quantity of coal supplied to the Chandrapur TPS. There is no separate contract for 80,000 MT diverted to Khaperkheda TPS. Thus, the Respondent had made the related deduction under Clause 8.7 of the Chandrapur Contract on the basis that there was no shortage of coal supplied to Khaperkheda TPS. 62. In any event the Arbitral Tribunal's interpretation of Clauses 8.7 and 8.11 of the Contract is a possible interpretation which calls for no interference by this Court under Section 34 of the Arbitration Act. The aforementioned decisions relie....