2019 (3) TMI 1924
X X X X Extracts X X X X
X X X X Extracts X X X X
.... Udayaditya Banerjee, AOR, Mr. Devashish Bharuka, AOR, Dr. (mrs. ) Vipin Gupta, AOR, Mr. V. N. Raghupathy, AOR, Mr. Anup Kumar, AOR, Mr. O. P. Bhadani, AOR, Mr. Rajesh Mahale, AOR, Mr. Anand Sanjay M. Nuli, Adv., Mr. Dharm Singh, Adv., Mr. Nanda Kumar, Adv. JUDGMENT S. Abdul Nazeer, J. 1. These appeals have been preferred Under Section 22 of the National Green Tribunal Act, 2010 (for brevity 'NGT Act') challenging the judgment and order dated 07.05.2015 and 04.05.2016 respectively passed by the Principal Bench of the National Green Tribunal, New Delhi (for short 'the Tribunal'). 2. The Appellants in Civil Appeal Nos. 5016 of 2016 and 8002-8003 of 2016 are Respondent Nos. 9 and 10 in the Original Application No. 222 of 2014 (hereinafter referred to as 'the Respondent Nos. 9 and 10'). The said Application was filed by Respondent Nos. 1 to 3 herein (hereinafter referred to as 'the applicants'). Respondent Nos. 4 to 7 in these appeals are the State of Karnataka and other authorities. They were arrayed as Respondent Nos. 1 to 4 in the application. Respondent Nos. 12 and 13 herein were subsequently impleaded in the application (for short 't....
X X X X Extracts X X X X
X X X X Extracts X X X X
....he Bellandur Lake and the Agara Lake. Respondent No. 9 was also directed to take protective measures to spare the buffer zone around Rajakaluves and also to commit that no construction would be carried out in the buffer zone. In the meeting of 11.11.2011, it was recorded that the project proposes car parking facility for 14,438 cars in that environmentally sensitive area. 6. It was alleged that NOC was issued covering an area of 17,404 sq. mtrs. whereas the built up area, as noted by SEAC, is 13,50,454.98 sq. mtrs. Respondent No. 9 obtained NOC from BWSSB by concealing material facts and by misrepresenting that NOC is required only for residential units which form a very minuscule part of the total project. Respondent No. 9 had approached the Karnataka State Pollution Control Board (for short 'the KSPCB') for obtaining clearance, which was granted on 04.09.2012 subject to the fulfillment of the conditions stated in the consent order which included leaving the buffer zone all along the valley and towards the lake. It is further contended that the grant of consent by the KSPCB to Respondent No. 9 also contained a condition with regard to obtaining Environmental Clearance f....
X X X X Extracts X X X X
X X X X Extracts X X X X
....nels. The applicants also relied on the Report of the Committee under the Chairmanship of Hon'ble Mr. Justice N.K. Patil suggesting immediate remedial action in order to remove encroachments on the lake area and the Rajakaluves and preservation of the lakes in and around Bangalore city. It was further contended that other Expert Committees, including Lakshman Rau Expert Committee had also submitted proposals for preservation, restoration or otherwise of the existing tanks in Bangalore Metropolitan Area which recommended to maintain good water surface in Bellandur tank and to ensure that the water in the tank is not polluted. The Central Government in August 2013 had issued an advisory on conservation and restoration of water bodies in the urban areas. The applicants claim to have obtained monitoring report of the project by Respondent No. 5, Ministry of Environment and Forests, through RTI on 21.08.2013. The report dated 14.08.2013 revealed that the project proponents are in clear breach of their undertaking to carry out all precautionary measures to ensure that the Bellandur lake is not affected by the construction and operational phase of the project. This approach is particu....
X X X X Extracts X X X X
X X X X Extracts X X X X
....tions contended that it was incorporated with the objective of establishing an Information Technology Park and R & D Centre with facilities such as residential complexes, parks, education centres and other allied infrastructure within a single compound. It had submitted the proposal to establish such Information Technology Park and other facilities to the State Government and requested for allotment of land for the project. Its proposal was considered in 78th High Level Committee meeting held on 21.06.2000 and after examining the proposal, it was approved by the Government on 06.07.2000. Before the State High Level Committee, it had informed that its requirement was 110 acres of land, 25 MW of power from the Karnataka Power Transmission Corporation Limited (for short the 'KPTCL'), and four lakh litres of water per day from BWSSB. The lands for the project were initially notified vide Notification dated 10.02.2004. Subsequently, the lands were allotted vide letter dated 28.06.2007 for which Lease-cum-Sale Agreement was signed on 30.06.2007. Considering the overall development of the State of Bangalore, this Respondent proposed a Mixed Use Development Project consisting of an....
X X X X Extracts X X X X
X X X X Extracts X X X X
....ls, machinery, infrastructure, medical and sanitary facilities, etc. and that it has availed financial assistance from various banks and financial institutions towards the construction and execution of the project and that various contracts have been signed with the third parties. It is specifically pleaded that the petition is barred by time and suffers from defects and laches. 14. Respondent No. 10 pleaded that the applicants raised multifarious proceedings against it which is an abuse of the process of law and mala fide. It had submitted a revised proposal in respect of its project in question and to obtain fresh clearance on 31.08.2007 with an investment of Rs. 179.22 crores. The State High Level Committee had cleared the project which was communicated to it on 25.01.2008. Its properties are located in between Bellandur Lake and Agara Lake but there are no primary storm water drains and secondary storm water drains that exist in its properties. It has clearances from various authorities, including Environmental Clearance and consent for establishment. 15. KIADB stated that after possession of the land was handed over to Respondent Nos. 9 and 10, one year time was granted ....
X X X X Extracts X X X X
X X X X Extracts X X X X
....runk, which originally formed the irrigation area for the adjoining agricultural lands. Therefore, it had questioned the decision of KIADB vide letter dated 06.07.2013 and even requested it to stop the construction activity and to re-classify the land as non-SEZ area. It was thereafter on 31.08.2013, that Respondent No. 9 wrote a letter for according approval for the proposed development projects. However, vide its letter dated 23.09.2013, LDA informed KIADB that it had no authority to grant or deny construction projects, but it also communicated its objections to KIADB mentioning that construction activity would be in contravention of the directions of the Supreme Court. Despite these warnings, KIADB granted approval to the extension of the building drawings of the project in favour of the project proponents with certain conditions, like ensuring that all natural valleys, valley zone, irrigation tanks and existing roads leading to villages in the said land should not be disturbed. Further, the natural sloping pattern of the project site was not to be altered and the lakes and other water bodies within and/or at the vicinity of the project area should be protected and conserved. De....
X X X X Extracts X X X X
X X X X Extracts X X X X
....ecretary of the Karnataka State Pollution Control Board shall act as the Convener of the Committee and would submit the final report to the Tribunal. 3) The Committee shall inspect not only the sites where the projects in question are located but even other areas of Bangalore which the Committee in its wisdom may consider appropriate, in order to examine the interconnectivity of lakes and impact of such activities upon the water bodies with particular reference to lakes. 4) The Committee shall submit whether the projects in question have encroached upon or are constructed on the wetlands and Rajakaluves. If so, are there any adverse environmental and ecological impact of these projects on the lake, particularly Bellandur Lake and Agara Lake, as well the Rajakaluves. The report should specify, if any Rajakaluves have been covered by the construction activities of Respondent Nos. 9 and 10 or by any of the projects in the area in question. 5) Committee should submit in its report, if these projects have any adverse impacts upon the surrounding ecology and environment, with particular reference to lakes and wetlands. If yes, then whether any....
X X X X Extracts X X X X
X X X X Extracts X X X X
....rom sanctioning any construction project on the wetlands and catchment areas of the water bodies in the city of Bangalore. 13) The Committee shall report if the project proponents are proposing to discharge their trade or domestic effluents into the lake or any of the water bodies in and around of the area in question. 14) For the reasons stated in the judgment, Respondent No. 9 is liable and shall pay a sum of Rs. 117.35 crores, while Respondent No. 10 shall pay a sum of Rs. 22.5 crores respectively being 5 per cent of the project value, within two weeks from today. The said amount would be paid to the KSPCB, which shall maintain a separate account for the same and would spend this amount for environmental and ecological restoration, restitution and other measures to be taken to rectify the damage resulting from default and non-compliance to law by the Project Proponent in that area, after taking approval of the Tribunal. 15) We make it clear that the said Respondents would not be entitled to pass on the amount in terms of direction 14, on to the purchasers because this liability accrues as a result of their own intentional defaults, di....
X X X X Extracts X X X X
X X X X Extracts X X X X
.... M.A. No. 603 of 2015 and M.A. No. 596 of 2015 These Applications have been filed on behalf of the Respondent 9 & 10 respectively. It is not necessary for us to refer to any details in view of the directions that we propose to issue in this case. Without prejudice to the rights and contentions of the parties and subject to just exception we would hear the parties in terms of the order of the Hon'ble Supreme Court of India primarily on the question of imposition of Environmental Compensation and merits attached in relation thereto. Parties are given liberty to address their submissions on that behalf. With the above directions the M.A. No. 603 of 2015 and M.A. No. 596 of 2015 stand disposed of without any order as to cost. 21. It is evident from the above orders that the Tribunal had granted opportunity to the parties to address it "limited question", as aforementioned. The Tribunal after hearing the parties passed an order dated 04.05.2016 as under: General Conditions or directions: 1. In view of our discussion in the main Judgment, we are of the considered view that the fixation of distance fro....
X X X X Extracts X X X X
X X X X Extracts X X X X
....d the entire area falls in critical zone in terms of ground water exploitation. Information reveals that only one million litre per month of STP treated water is used by builders for construction purposes. For this reason, the BWSSB issues partial NOC to various residential and commercial projects in respect of supply of potable water. In this context, following directions need to be issued: i. At the time of grant of EC, the water requirement for the construction phase and operation phase should be considered separately. Due consideration should also be given for identification of source of supply of water and this should be a pre-requisite for grant of EC. ii. All the project proponents should necessarily use only treated sewage water for construction purpose and this should be reflected in EC as a condition for construction phase. iii. Wherever the quality of treated sewage water does not conform to the quality needed for construction, necessary upgradation in STP should be undertaken immediately. Specific Conditions/Directions for Respondent 9; In addition to the above directions which should be equally ....
X X X X Extracts X X X X
X X X X Extracts X X X X
....d not to be considered as part of green belt of the project as part of EC condition and will be over and above the green belt as indicated in the EC. vii. In view of the heavy traffic load in the adjoining Sarjapur road, a proper study on the basis of traffic density, foot falls expected, etc., a proper plan needs to be prepared and the concept of service road exclusively for the project needs to be worked out and additional parking space created within the project area and incorporated as a part of the overall project layout, within a period of 3 months. 10. Though, at the time of hearing prior to passing the Judgment, we had heard the parties on all aspects but still we have provided re-hearing to the parties on all issues with emphasis on imposition of environmental compensation including the quantum. Upon hearing, we are of the considered view that environmental compensation imposed upon Respondent No. 9 calls for no variation and the Respondent No. 9 should be called upon to pay the said amount of Rs. 117.35 Crores determined under the judgment prior to commencement of any project activity at the site. Respondent No. 10 has not commenced any actua....
X X X X Extracts X X X X
X X X X Extracts X X X X
....0 shall ensure that debris or any construction material that has been dumped into the Rajkulewas, or on their Banks and on the buffer zone of wetlands should be removed within four weeks from today. In the event they fail to do so, the same shall be removed by the Lake Development Authority along with the State Administration and recover charges thereof from the said Respondents. 6. There is a serious discrepancy even in regard to the measurement of land as far as Respondent No. 9 is concerned. Admittedly the Respondent has been allotted and is in possession of land admeasuring 63.94 acres, though Environmental Clearance has been granted for 2,92,636.03 Sq. Meters which is equivalent to 72.22 acres. For this reason alone, Environmental Clearance cannot be given effect to. While issuing the amended Environmental Clearance, SEIAA Karnataka shall take into consideration all these aspects and, if necessary, would require Respondent No. 9 to submit a fresh layout plant and the entire project may be revised in accordance with law. 7. Both the Respondents (Project Proponents) shall submit an appropriate plan in view of the conditions imposed in this judgment ....
X X X X Extracts X X X X
X X X X Extracts X X X X
....ht to have dismissed the application on the ground that as it is barred by time. 24. It was also argued that buffer zone laid down by the NGT is substantially higher as compared to buffer zone which is required to be maintained as per the Revised Master Plan, 2015 issued on 22.06.2007. This is contrary to the Karnataka Town and Country Planning Act, 1961 (for short 'the Planning Act'). 25. Shri Neeraj Kishan Kaul and Shri R. Venkataramani, learned senior Counsel appearing for the Appellants, in this case have also made similar submissions. It was argued that the direction imposing penalty/compensation is illegal on the ground that the applicants did not allege that the construction work of the project has caused environmental wrong. No wrong or injury either to Bellandur lake water body or to Bellandur lake area, has been alleged and established. As such, there is no question of any enquiry relating to imposition of penalty or any compensation. 26. Shri Maninder Singh, learned senior Counsel appearing for the Appellants, in C.A. Nos. 5016 and 10995 of 2016, while supporting the submissions made by Shri Rohatgi, has submitted that the Appellant has obtained sanction....
X X X X Extracts X X X X
X X X X Extracts X X X X
....he Appellants in other appeals including the State of Karnataka are concerned. He has also no objection to set aside the general conditions and directions of the NGT in paragraph (1) of the order dated 04.05.2016 except the directions issued against Respondent Nos. 9 and 10. In view of the above, it is not necessary to examine the contentions of the learned Advocate General in Civil Appeal Nos. 4923-4924 of 2017. It is also not necessary to consider the contentions urged in the other civil appeals except the appeals filed by Respondents Nos. 9 and 10. 30. Shri Poovayya has strongly opposed the submissions made by the learned senior Counsel appearing for the Appellants in C.A. No. 5016 of 2016 and C.A. Nos. 8002-8003 of 2016. It is submitted that the Tribunal is a specialized body for effective and expeditious disposal of cases relating to environmental protection and conservation of forests and other natural resources including enforcement of any legal right relating to environment. The jurisdiction of the Tribunal is provided Under Sections 14, 15 and 16 of the NGT Act. Section 14 provides for the jurisdiction over all civil cases where a substantial question relating to enviro....
X X X X Extracts X X X X
X X X X Extracts X X X X
....pensation or relief first arose. 33. It was further submitted that right to appeal Under Section 22 is not a vested right unless provided by statute. Exercise of Appellate Jurisdiction without the fulfillment of statutory mandate would be without jurisdiction. Section 22 of the Act provides for an appeal on the ground specified in Section 100 of the Code of Civil Procedure, 1908 (for short 'the CPC'). Under Section 100 of the Code of Civil Procedure, an appeal can be filed only on the ground that the case involves a substantial question of law as may be framed by the Appellate Court. In the instant case, the appeal does not involve any substantial question of law hence it has to be dismissed in limine. He has taken us through various materials placed on record in order to substantiate that the direction passed and penalty imposed by the Tribunal upon to project proponents are sustainable. He prays for dismissal of the appeals. 34. We have carefully considered the submissions of the learned Counsel of the parties and perused the materials placed on record. 35. Before considering the other contentions of the learned Counsel for the parties, let us first consider the ....
X X X X Extracts X X X X
X X X X Extracts X X X X
....s. If the question is settled by the highest court or the general principles to be applied in determining the question are well settled and there is a mere question of applying those principles or that the plea raised is palpably absurd the question would not be a substantial question of law. 38. It is equally settled that merely because the remedy of appeal is provided against the decision of the Tribunal on a substantial question of law alone, that does not ipso facto permit the Appellants to agitate their appeal to seek re-appreciation of the factual matrix of the entire matter. The Appellants cannot seek to re-argue their entire case to seek wholesale re-appreciation of evidence and the factual matrix that has been considered by the Tribunal is ex facie impermissible Under Section 22. There cannot be fresh appreciation or re-appreciation of facts and evidence in a statutory appeal under this provision. 39. The first question raised by the learned Counsel is in relation to the maintainability of the application before the Tribunal. 40. The Tribunal has been established under a constitutional mandate provided in Schedule VII List I Entry 13 of the Constitution of India, ....
X X X X Extracts X X X X
X X X X Extracts X X X X
....ishore Lal v. Chairman, Employees' State Insurance Corporation (2007) 4 SCC 579, para 17). The existence of the Tribunal without its broad restorative powers Under Section 15(1)(c) read with Section 20 of the Act, would render it ineffective and toothless, and shall betray the legislative intent in setting up a specialized Tribunal specifically to address environmental concerns. The Tribunal, specially constituted with Judicial Members as well as with Experts in the field of environment, has a legal obligation to provide for preventive and restorative measures in the interest of the environment. 45. Section 15 of the Act provides power & jurisdiction, independent of Section 14 thereof. Further, Section 14(3) juxtaposed with Section 15(3) of the Act, are separate provisions for filing distinct applications before the Tribunal with distinct periods of limitation, thereby amply demonstrating that jurisdiction of the Tribunal flows from these Sections (i.e. Sections 14 and 15 of the Act) independently. The limitation provided in Section 14 is a period of 6 months from the date on which the cause of action first arose and whereas in Section 15 it is 5 years. Therefore, the legisl....
X X X X Extracts X X X X
X X X X Extracts X X X X
....cording to them, it is much beyond the prescribed period of limitation. Also, there is no application for condonation of delay accompanying the main application. Therefore, the Tribunal will not have jurisdiction to condone the delay. 49. The OA No. 222 of 2014 was not an application simpliciter Under Section 14 of the Act. It was an application where a specific prayer has been made with reference to Lake Development Authority's ("LDA") Report dated 12.06.2013 and the Ministry of Environment, Forest and Climate Change ("MoEF") Monitoring Committee Report dated 14.08.2013 for restoration of ecologically sensitive land and for maintaining the sensitive in its natural condition so that the ecological balance of the area is not disturbed. It is clear from the documentary evidence supported by data, that the project proponents have committed breaches and the implementation of the project is bound to have serious adverse impact on the ecology, hydrology and the environment in the catchment area of Bellandur Lake. The environmental degradation as established from the documents would give rise to an independent cause of action. Therefore, this was a petition Under Section 15 of the ....
X X X X Extracts X X X X
X X X X Extracts X X X X
....lative adverse effects of the activities undertaken by the Respondents before us can be summed up as under: 1) The construction of both the projects had started prior to the grant to Environmental Clearance. 2) The EIA Notification of 2006 requires that without grant of Environmental Clearance, no project can commence its activity. This restriction applies not only to operationalization of the project but even for the purposes of establishment. 3) Revenue Map images shows multiple Rajakaluves flowing through the project(s) in question. The images further show encroachment on Rajakaluves. 4) Digital images of the land available on Google satellite images showing encroachment on two major Rajakaluves. 5) Google Satellite images retrieved from Google archives clearly reflect two distinct features. Firstly, change in the wetland area between the period of 13th November, 2000 and 23rd November, 2010. Secondly, it reveals the excavation work carried out by Respondent Nos. 9 and 10 commenced prior to obtaining Environmental Clearance. 6) Restriction in regard to extraction of ground water was not str....
X X X X Extracts X X X X
X X X X Extracts X X X X
....f factual matrix by this Court Under Section 22 of the NGT Act. 56. Shri R. Venkataramani, learned senior Counsel has also raised a subsidiary issue relating to res judicata. According to him, Respondent Nos. 12 and 13 filed Writ Petition Nos. 3656-57/2013 seeking similar reliefs in a representative capacity. The issues raised therein are same as those canvassed in the application before the Tribunal. The reliefs sought for are essentially the same. Hence, the applications are barred by the principle of res judicata. 57. The Tribunal has answered this issue in paragraphs 47 to 51 of the order. There was no dispute in so far as filing of the writ petitions is concerned. However, the parties are not common nor the issues in application and the writ petitions are directly and substantially the same. After examination of the pleadings, the Tribunal has recorded a finding of fact that there is no commonality of a cause of action or likelihood of a conflict between the judgments. The prayers and the geneses of the respective proceedings are entirely distinct and different in their scope and relief. The issues before the Tribunal would essentially relate to environment ecology and i....
X X X X Extracts X X X X
X X X X Extracts X X X X
....e main Judgment, we are of the considered view that the fixation of distance from water bodies (lakes and Rajkalewas) suffers from the inbuilt contradiction, legal infirmity and is without any scientific justification. The RMP - 2015 provides 50m from middle of the Rajkalewas as buffer zone in the case of primary Rajkalewas, 25m in the case of secondary Rajkulewas and 15m in the tertiary Rajkulewas in contradiction to the 30m in the case of lake which is certainly much bigger water body and its utility as a water body/wetland is well known certainly part of wet land. Thus, we direct that the distance in the case of Respondents Nos. 9 and 10 from Rajkulewas, Waterbodies and wetlands shall be maintained as below: (i) In the case of Lakes, 75m from the periphery of water body to be maintained as green belt and buffer zone for all the existing water bodies i.e. lakes/wetlands. (ii) 50m from the edge of the primary Rajkulewas. (iii) 35m from the edges in the case of secondary Rajkulewas (iv) 25m from the edges in the case of tertiary Rajkulewas This buffer/green zone would be treated as no construction zone for all intent and p....
TaxTMI