Just a moment...

Top
Help
×

By creating an account you can:

Logo TaxTMI
Call Us / Help / Feedback

Contact Us At :

E-mail: [email protected]

Call / WhatsApp at: +91 99117 96707

For more information, Check Contact Us

FAQs :

To know Frequently Asked Questions, Check FAQs

Most Asked Video Tutorials :

For more tutorials, Check Video Tutorials

Submit Feedback/Suggestion :

Email :
Please provide your email address so we can follow up on your feedback.
Category :
Description :
Min 15 characters0/2000
TMI Blog
Home / TMI Blogs / RSS

1990 (1) TMI 293

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....Commissioner.   2. The facts pertinent for the decision of this tax revision case are as follows: The revision petitioner, Waves Electronics (P.) Ltd., is engaged in the manufacture and sale of electrical goods and it also undertakes contracts for designing, execution and installation of various electrical goods. For the assessment year 1979-80, the petitioner filed a return for Rs. 5,91,332.60 and it did not include in the return the amount of Rs. 1,35,411 which it received towards fabrication, supply and installation of M.V. switch boards for Kunnathara Textiles Ltd., Calicut. That work was executed in pursuance of an order placed by them on November 8, 1977. That amount is not included in the taxable turnover as it represents ....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....to the customer. Shri Mohamed Kutty contends that numerous decisions of the Supreme Court and the High Courts have categorically held that contracts where majority of the value is for the work done are works contracts, though incidentally some goods are sold in such works contracts, especially the material involved in the works contracts has necessarily to be sold to the customer. He places reliance upon the very decisions which are referred to by the Tribunal in its order. 4.. On behalf of the Revenue-respondent, the Government Pleader contends that this is a case where the switch boards are to be assembled as per the specifications and designs given by the party and the value of the skill involved in assembling and fabricating the swit....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

.... boards supplied shall be guaranteed for a period of 12 months against defective design, materials and workmanship. The specifications enclosed are given at page 23. A perusal of page 23 clearly indicates that the very drawings are to be prepared by the assessee. Preparation of drawing, designing, assembling, supply and erection has to be done by the assessee. The clause relating to inspection, testing and trial run clearly stipulates that the switch boards will be finally accepted only after supply, erection, commissioning and trial run to the satisfaction of the receiving party. As regards the clause relating to components, it clearly stipulates that the components should be of the best possible grade, and the list of components and the m....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....e findings of fact, we shall now examine the reasons given by the Tribunal and the decisions relied on by the Tribunal in support of its decision. 6.. The Tribunal looking at the table of rates given in the contract came to the conclusion that there are two contracts, and that the first contract is for the supply of switch boards and the second contract is for installation. It failed to give importance to the element of designing and fabrication. Referring to the decision in State of Madras v. Richardson Cruddas Ltd. [1968] 21 STC 245 (SC), it quoted a passage from Halsbury's Laws of England, Vol. 34, page 6. But it failed to apply the crucial test indicated in that passage. The crucial test indicated in that passage is: "The test is ....

X X   X X   Extracts   X X   X X

Full Text of the Document

X X   X X   Extracts   X X   X X

....rice agreed or it is primarily a contract for work and labour, and materials are supplied in execution of such contract. If we apply the test to the facts of this case, we find that the contract is a works contract. 8.. In the penultimate paragraph of the Tribunal's order, the Tribunal committed a factual mistake in thinking that the drawings were supplied by the customer. A perusal of the contract and the specifications clearly indicates that the drawings are to be made by the petitioner-assessee, who undertook the works contract. Only specifications were given by the customer and various standards were insisted upon for the work that is to be executed. 9.. Judging from whatever angle, we find that the contract is a works contract. T....