Faceless assessment and registration procedures are updated through electronic communication, revised recovery rules, extended deadlines, and replacem...
Risk-based selective vessel boarding requires accurate declarations and preserves master and agent liability where physical inspections are not select...
Permanent-establishment reassessment cannot revisit scrutinised disclosures; extended reopening fails without undisclosed material facts and within st...
A post-01.07.2017 works contract was held to fall under the GST regime, so the contractor could not insist on the pre-GST tax rate. Clause 42.1 was construed to entitle reimbursement of Central and State taxes actually levied and paid on completed items of work, and CGST/SGST were held covered within that expression. The absence of an incorporated Schedule A could not defeat the contractual reimbursement right. GST returns and portal statements were accepted as proof of payment. The refusal to reimburse was found arbitrary and violative of Article 14, and interest at 12% per annum was awarded from the respective dates of payment. The writ petition was held maintainable because the dispute turned on contract interpretation, not disputed facts.
A post-01.07.2017 works contract was held to fall under the GST regime, so the contractor could not insist on the pre-GST tax rate. Clause 42.1 was construed to entitle reimbursement of Central and State taxes actually levied and paid on completed items of work, and CGST/SGST were held covered within that expression. The absence of an incorporated Schedule A could not defeat the contractual reimbursement right. GST returns and portal statements were accepted as proof of payment. The refusal to reimburse was found arbitrary and violative of Article 14, and interest at 12% per annum was awarded from the respective dates of payment. The writ petition was held maintainable because the dispute turned on contract interpretation, not disputed facts.
Note: It is a system-generated summary and is for quick reference only.