Tribunal upholds stay on termination notice, stresses compliance with Insolvency and Bankruptcy Code The Tribunal upheld the stay on the termination notice issued by the Appellant, emphasizing compliance with the Facilities Agreement and the moratorium ...
Cases where this provision is explicitly mentioned in the judgment/order text; may not be exhaustive. To view the complete list of cases mentioning this section, Click here.
Provisions expressly mentioned in the judgment/order text.
Tribunal upholds stay on termination notice, stresses compliance with Insolvency and Bankruptcy Code
The Tribunal upheld the stay on the termination notice issued by the Appellant, emphasizing compliance with the Facilities Agreement and the moratorium under Section 14 of the Insolvency and Bankruptcy Code. It highlighted the Resolution Professional's duties in maintaining the 'Corporate Debtor' as a going concern. The Tribunal dismissed the appeal, affirming the Adjudicating Authority's decision to stay the termination notice and directing the Appellant to comply with the Agreement terms, with no costs awarded.
Issues Involved: 1. Validity of the termination notice issued by the Appellant. 2. Compliance with the Facilities Agreement's termination clause. 3. Applicability of the moratorium under Section 14 of the Insolvency and Bankruptcy Code (IBC). 4. Duties and responsibilities of the Resolution Professional during the Corporate Insolvency Resolution Process (CIRP).
Issue-wise Detailed Analysis:
1. Validity of the termination notice issued by the Appellant: The Appellant argued that the termination notice dated 10th June 2019 was issued in accordance with Clause 11(b) of the Facilities Agreement due to the 'Corporate Debtor's' failure to remedy contractual breaches. The Respondent, however, contended that no prior notice was received to cure the material breach, making the termination notice invalid. The Tribunal noted that the CIRP against the 'Corporate Debtor' was initiated on 29th March 2019, and the termination notice was issued subsequently. The Tribunal emphasized that the moratorium imposed under Section 14 of the IBC prohibits such termination actions.
2. Compliance with the Facilities Agreement's termination clause: Clause 11(b) of the Facilities Agreement stipulates that either party may terminate the agreement with a written notice if the material breach is not cured within 30 days of receipt of the notice. The Appellant claimed to have issued multiple notices seeking remedies for breaches, which the 'Corporate Debtor' failed to address, leading to the termination notice. However, the Respondent argued that they did not receive any such notice and had cured all deficiencies. The Tribunal found that the termination notice was issued without adhering to the mandatory notice period required by Clause 11(b).
3. Applicability of the moratorium under Section 14 of the Insolvency and Bankruptcy Code (IBC): The Tribunal highlighted that Section 14(1) of the IBC imposes a moratorium prohibiting actions like the institution of suits, transferring assets, and recovery of property by owners or lessors. The Adjudicating Authority's order dated 29th March 2019, which admitted the application under Section 7 of the IBC, imposed such a moratorium. The Tribunal emphasized that the moratorium aims to ensure the smooth functioning of the 'Corporate Debtor' as a going concern during the CIRP.
4. Duties and responsibilities of the Resolution Professional during the Corporate Insolvency Resolution Process (CIRP): The Tribunal reiterated that the Resolution Professional, upon the imposition of the moratorium, takes control of the 'Corporate Debtor' and must ensure its operations continue smoothly. The Resolution Professional's duties include preserving and protecting the assets of the 'Corporate Debtor' and representing the 'Corporate Debtor' in judicial or quasi-judicial proceedings. In this case, the Resolution Professional sought to stay the termination of the Facilities Agreement to maintain the 'Corporate Debtor' as a going concern, which aligns with the objectives of the IBC.
Conclusion: The Tribunal concluded that the Adjudicating Authority rightly stayed the termination notice and directed the Appellant to adhere to the terms of the Facilities Agreement. The Tribunal found no illegality in the Adjudicating Authority's order dated 18th December 2019, and accordingly, the appeal was dismissed with no orders as to costs.