Tribunal partially allows appeals, directs re-evaluation for compliance. Transfer Pricing Adjustment remitted for lack of evidence. The Tribunal partly allowed all appeals, directing re-evaluation by lower authorities for compliance with statutory provisions and principles of natural ...
Cases where this provision is explicitly mentioned in the judgment/order text; may not be exhaustive. To view the complete list of cases mentioning this section, Click here.
Provisions expressly mentioned in the judgment/order text.
Tribunal partially allows appeals, directs re-evaluation for compliance. Transfer Pricing Adjustment remitted for lack of evidence.
The Tribunal partly allowed all appeals, directing re-evaluation by lower authorities for compliance with statutory provisions and principles of natural justice. The Transfer Pricing Adjustment related to project expenses and sales support services was remitted for re-adjudication due to lack of documentary evidence and ignoring the assessee's submissions. The use of multiple-year data was rejected, while the benefit of +/-5% was granted. Penalty proceedings were noted as consequential, and general grounds were disposed of accordingly. In AY 2008-09 and 2009-10, TP adjustments were remitted back for re-evaluation, emphasizing justification of methodologies and compliance.
Issues Involved: 1. Transfer Pricing Adjustment – Payment of Project Expenses 2. Transfer Pricing Adjustment – Provision of Sales Support Services 3. Use of Multiple Year Data 4. Benefit of +/-5% 5. Initiation of Penalty Proceedings 6. General
Detailed Analysis:
1. Transfer Pricing Adjustment – Payment of Project Expenses: The assessee, a subsidiary of Jotun AS, Norway, engaged in trading decorative paints and sales support services, was assessed at a loss after certain transfer pricing (TP) adjustments. The TP adjustment concerning project expenses amounted to Rs. 172.46 Lacs, which the assessee claimed were reimbursed to its AE on a cost-to-cost basis. The Ld. TPO proposed a TP adjustment of Rs. 82.96 Lacs due to a lack of documentary evidence. The Ld. DRP enhanced the adjustment, viewing the expenses as part of shareholders' activities, resulting in an additional adjustment of Rs. 89.49 Lacs. The Tribunal found that the Ld. DRP's conclusion lacked plausible reasoning and violated the principle of natural justice. It remitted the matter back to the AO/TPO for re-evaluation, emphasizing that the expenditure was directly related to the project being set up and should be substantiated with necessary explanations and documentary evidence.
2. Transfer Pricing Adjustment – Provision of Sales Support Services: The assessee provided sales support services amounting to Rs. 2.01 Crores to its AE in Singapore, which were benchmarked using the Transactional Net Margin Method (TNMM). The Ld. TPO apportioned the total cost, resulting in a PLI of (-)25.37% and a TP adjustment of Rs. 74.37 Lacs. The Tribunal noted that the assessee's submissions regarding cost allocation and determination of ALP were ignored by the lower authorities. It remitted the matter back to the AO/TPO for re-adjudication, directing that the ALP of transactions be computed within the statutory framework and the assessee substantiate its stand.
3. Use of Multiple Year Data: The assessee pleaded for the use of multiple-year data, but the Tribunal found no merit in this ground. It upheld the preference for single-year data of the impugned AY as per Rule-10B(4), thus rejecting this ground for all three years.
4. Benefit of +/-5%: The Tribunal allowed this ground for statistical purposes, stating that any concessions or benefits available to the assessee under statutory provisions should be granted.
5. Initiation of Penalty Proceedings: This ground was noted as consequential and did not require specific adjudication.
6. General: This ground was general in nature and disposed of in line with the above orders.
Additional Issues in AY 2008-09 and 2009-10: In AY 2008-09, the assessee faced a TP adjustment of Rs. 806.87 Lacs, including Rs. 415.04 Lacs against import of finished goods. The Tribunal found that the methodology adopted by the assessee using Resale Price Method (RPM) was not justified due to the significant marketing expenditure incurred. It remitted the matter back to the AO/TPO for re-evaluation, directing the assessee to justify the methodology and selection of comparables. Similarly, for AY 2009-10, the TP adjustment against project expenses was remitted back for re-evaluation.
Conclusion: All appeals were partly allowed for statistical purposes, with directions for re-evaluation and re-adjudication by the lower authorities, ensuring compliance with statutory provisions and principles of natural justice. The order was pronounced in the open court on 04th May 2018.