Just a moment...
Convert scanned orders, printed notices, PDFs and images into clean, searchable, editable text within seconds. Starting at 2 Credits/page
Try Now →Press 'Enter' to add multiple search terms. Rules for Better Search
Use comma for multiple locations.
---------------- For section wise search only -----------------
Accuracy Level ~ 90%
Press 'Enter' after typing page number.
Press 'Enter' after typing page number.
No Folders have been created
Are you sure you want to delete "My most important" ?
NOTE:
Press 'Enter' after typing page number.
Press 'Enter' after typing page number.
Don't have an account? Register Here
Press 'Enter' after typing page number.
Issues: (i) Whether the question of delay in completion of work and the consequent levy of compensation fell within the arbitrator's jurisdiction or was an excepted matter under the contract; (ii) Whether the award of labour cess, DVAT, escalation and overheads suffered from patent illegality or breach of contract; (iii) Whether the dismissal of the counterclaim called for interference under Section 34 and Section 37 of the Arbitration and Conciliation Act, 1996.
Issue (i): Whether the question of delay in completion of work and the consequent levy of compensation fell within the arbitrator's jurisdiction or was an excepted matter under the contract.
Analysis: Clause 2 of the agreement made the authority's decision final only on the quantification of compensation payable for delay. The existence of delay and the question whether the contractor was responsible for it remained open to adjudication and were capable of being decided by the arbitral tribunal. The tribunal therefore did not enter an excepted matter when it examined whether the delay was attributable to the contractor and whether compensation could at all be recovered. The determination of delay was treated as arbitrable, while only the quantum fixed by the authority was excluded.
Conclusion: The issue was held to be arbitrable, and the award of compensation was sustained in favour of the respondent.
Issue (ii): Whether the award of labour cess, DVAT, escalation and overheads suffered from patent illegality or breach of contract.
Analysis: The award on labour cess and DVAT was upheld because those deductions were not part of the approved rates and the tribunal relied on the contractual and rate-analysis material on record. The escalation claim was sustained because the prolonged delay had extended the execution period far beyond the original term, and the tribunal adopted the CPWD indices as the appropriate basis for computation. The overheads were also allowed on the footing that prolongation of work necessarily caused additional overhead burden, and the amount was moderated by applying the Hudson formula. These determinations were based on evidence, contractual interpretation and factual appreciation, and did not disclose perversity.
Conclusion: The awards under this head were upheld and the challenge failed.
Issue (iii): Whether the dismissal of the counterclaim called for interference under Section 34 and Section 37 of the Arbitration and Conciliation Act, 1996.
Analysis: The counterclaim for loss of reputation and loss of work was found to be unsupported by contemporaneous assertion or evidence of actual loss. The tribunal treated it as conjectural and as a counterblast to the claim, and the findings were accepted as reasoned and evidence-based. In proceedings under Section 34 and Section 37, interference is confined to cases of patent illegality, public policy violation or similar exceptional grounds, none of which was made out.
Conclusion: The dismissal of the counterclaim was affirmed.
Final Conclusion: The arbitral award and the order under Section 34 were held to be reasoned and within jurisdiction, and no ground for appellate interference was made out.
Ratio Decidendi: In a contract containing an excepted-matter clause, the tribunal may decide whether the contractor was responsible for delay, while the contractual authority's decision remains final only on quantification of compensation; concurrent factual findings on claims based on evidence will not be interfered with under Section 34 or Section 37 absent patent illegality or public policy violation.