Just a moment...
Press 'Enter' to add multiple search terms. Rules for Better Search
Use comma for multiple locations.
---------------- For section wise search only -----------------
Accuracy Level ~ 90%
Press 'Enter' after typing page number.
Press 'Enter' after typing page number.
No Folders have been created
Are you sure you want to delete "My most important" ?
NOTE:
Press 'Enter' after typing page number.
Press 'Enter' after typing page number.
Don't have an account? Register Here
Press 'Enter' after typing page number.
Issues: Whether a solar power developer that commissioned its project after the control period in the earlier tariff order and did not avail accelerated depreciation could nevertheless claim the tariff under the later tariff order despite the terms of the power purchase agreement.
Analysis: The tariff orders and the power purchase agreement had to be read together. The earlier tariff order fixed tariff on the footing that projects would take the benefit of accelerated depreciation, while also indicating that a separate tariff could be determined where that benefit was not available. The agreement, however, expressly tied the payable tariff to the tariff order in force and further provided that if commissioning was delayed beyond the stipulated date, the lower of the agreed tariff and the tariff effective on the date of commissioning would apply. The developer's choice under the Income-tax Act to forgo accelerated depreciation did not override the contractual commitment already undertaken under the agreement. The later tariff order could not be invoked as an automatic contractual entitlement merely because the project was commissioned after the earlier control period.
Conclusion: The developer was not entitled to claim the tariff fixed in the later tariff order as a matter of contract. The impugned orders were unsustainable and were set aside, and relief was granted to the appellant.