Just a moment...
Press 'Enter' to add multiple search terms. Rules for Better Search
Use comma for multiple locations.
---------------- For section wise search only -----------------
Accuracy Level ~ 90%
Press 'Enter' after typing page number.
Press 'Enter' after typing page number.
No Folders have been created
Are you sure you want to delete "My most important" ?
NOTE:
Press 'Enter' after typing page number.
Press 'Enter' after typing page number.
Don't have an account? Register Here
Press 'Enter' after typing page number.
Issues: Whether the dispute resolution procedure under Clauses 24 and 25 of the contract was mandatory so as to bar arbitration for failure to approach the DRE within 14 days, and whether a quantified claim already referred to arbitration could be amended before the arbitral tribunal without restarting the contractual pre-arbitral procedure.
Analysis: The petition under Section 34 of the Arbitration and Conciliation Act, 1996 was confined to the objection that the contractor had not strictly followed the contractual route of reference to the Engineer and then to the Dispute Review Expert. The Court held that Clause 24.1 did not prescribe a strict limitation period or create any consequence making the Engineer's decision final and binding merely because a DRE reference was not made within 14 days. The requirement was treated as directory, intended to ensure contemporaneous pursuit of the dispute, and a rigid construction was found unreasonable. The Court also noted that the Engineer had given only a cryptic rejection, making it for the contractor to seek clarification before approaching the DRE. Further, Clause 3 of the Special Conditions permitted arbitration when a dispute arose, independent of the alleged procedural sequence. On the second objection, the Court held that once a dispute has been referred to arbitration, a mere change in the quantum claimed does not amount to a fresh dispute requiring re-invocation of the Engineer/DRE process. The arbitral tribunal retained power under the Act to permit amendment of the claim amount.
Conclusion: The procedural objections were rejected. The contractual pre-arbitral mechanism was not mandatory in the sense contended, and amendment of the quantified claim before the arbitral tribunal was permissible.
Ratio Decidendi: A contractual clause requiring reference to a dispute review mechanism within a stated time is directory, not mandatory, unless the contract clearly makes delay fatal; once a dispute is validly before arbitration, amendment of its quantification does not require the dispute to be restarted through the pre-arbitral procedure.