Just a moment...
Press 'Enter' to add multiple search terms. Rules for Better Search
When case Id is present, search is done only for this
No Folders have been created
Are you sure you want to delete "My most important" ?
NOTE:
Don't have an account? Register Here
<h1>Court Sanctions Settlement for Undervalued Property Sale</h1> <h3>M/s. Globe Associates (P) Ltd Versus Amar Singh and Co. and Others</h3> M/s. Globe Associates (P) Ltd Versus Amar Singh and Co. and Others - TMI ISSUES PRESENTED AND CONSIDERED 1. Whether an application for transfer/registration of leasehold rights was submitted to the municipal development authority and, if so, the legal consequence of that submission for computation of unearned increase. 2. On what date the unearned increase is to be calculated for the purpose of transfer of leasehold rights - date of application or date of approval/mutation by the Competent Authority. 3. Whether the municipal development authority is bound by provisional calculations of unearned increase furnished in court proceedings and by earlier provisional figures communicated during compromise negotiations. 4. Whether interest is payable on the unearned increase, and if so, the appropriate rate and period for which interest should run in the circumstances of the case. 5. Whether an authority can insist on calculation and payment of additional sums (misuse charges, damages, compounding charges) before considering transfer, and the effect of such insistence on computation of unearned increase. ISSUE-WISE DETAILED ANALYSIS Issue 1 - Existence and legal effect of an application to the Authority for determination of unearned increase Legal framework: Transfer of leasehold rights under the development authority's regime requires an application for approval/mutation; unearned increase is determined with reference to the date of application in authority jurisprudence and practice. Precedent treatment: The Court referred to established principle that unearned increase is calculated as on the date of application (citing relevant Supreme Court authority on point) and examined documentary and oral court-record materials to determine whether such application was made. Interpretation and reasoning: The Court considered contemporaneous court orders, statements by counsel, the authority's conduct in taking adjournments, and an unrebutted affidavit producing a copy of an application dated 2.7.1985. The Court inferred from (a) the role the authority played in compromise negotiations, (b) express directions to approach the authority, (c) recorded statements that an application had been made, and (d) forensic improbability that no application was filed given the settlement steps, that an application was in fact submitted on 2.7.1985. Ratio vs. Obiter: Ratio - where contemporaneous court records, parties' conduct and an uncontroverted affidavit support the filing of an application, a court may find the application was made for the limited purpose of fixing the date for computation of unearned increase. Obiter - remarks on the improbability of a party not filing an application when it was necessary for settlement. Conclusion: The Court held that an application for determination of unearned increase was made on 2.7.1985 and treated that date as operative for further calculations. Issue 2 - Proper date for computation of unearned increase (date of application v. date of approval) Legal framework: The authority's policy and prior judicial decisions indicate unearned increase is to be computed with reference to market/rate tables prevailing on the date of the application for transfer/permission to sell; calculations based on rates at the time of approval are not appropriate where an application date can be established. Precedent treatment: The Court relied on Supreme Court authority holding that unearned increase is calculated as on the date of application. The authority's submissions that rates ought to be applied as on the date of approval were considered and rejected in view of established precedent. Interpretation and reasoning: The Court observed that permitting computation on the date of approval would allow the authority's delay to prejudice the applicant. The development authority itself in its affidavits accepted that pre-determined rates as on the date of application are the basis, even if provisional calculations were made later; the Court therefore applied the principle against allowing administrative delay to shift the operative date. Ratio vs. Obiter: Ratio - unearned increase shall be calculated using the pre-determined market rate prevailing on the date of the application (2.7.1985) where that application is shown to have been made. Obiter - observations on unfairness of tying computation to date of approval when authority has delayed consideration. Conclusion: The unearned increase must be calculated on the basis of pre-fixed market rates prevailing as on 2.7.1985 (the date of the application found to have been submitted), not on the date of approval/mutation. Issue 3 - Binding effect of provisional calculations and earlier figures provided during compromise negotiations Legal framework: Provisional calculations provided by an authority during negotiations or court proceedings may inform parties but do not necessarily bind the authority as final unless an application is processed and a final determination is made according to statutory/policy procedures. Precedent treatment: The Court noted the authority's position that figures supplied earlier were provisional and that final rates depend on the rates prevailing at the time of formal approval; a later Supreme Court decision relied on by the authority was found to be an order based on compromise and not laying down a contrary legal proposition. Interpretation and reasoning: The Court distinguished between provisional figures supplied for negotiation and a legally operative determination. However, because the application date was established, the Court concluded that the authority must compute unearned increase based on pre-fixed market rates as on the established application date; this narrows the scope of the authority's contention that it was not bound by provisional figures. Ratio vs. Obiter: Ratio - provisional figures communicated during compromise do not bind the authority as final unless a formal determination is made, but where an application date is proved, the authority must use the pre-determined rates of that application date in computing unearned increase. Obiter - criticism of reliance on a prior compromise order as laying down law. Conclusion: The authority is not bound by earlier provisional figures per se, but must calculate unearned increase on the pre-determined market rates applicable as of the date of the proven application (2.7.1985); prior provisional calculations furnished in court do not override this rule. Issue 4 - Liability to pay interest on unearned increase and the appropriate rate/period Legal framework: Where payment of statutory dues is deferred, courts may direct payment with interest to compensate for delay; the rate is a matter for court determination in light of equities and authority submissions. Precedent treatment: The Court considered the authority's claim for interest at 18% p.a. on provisional calculations but was guided by the need for equitable allocation of interest in the factual matrix. Interpretation and reasoning: Balancing the parties' conduct and the authority's role in delaying finalization, the Court fixed interest at 9% p.a. from the date of the application (2.7.1985) till payment. The Court treated interest as compensatory but moderated the rate from the authority's claimed 18% to 9% in the peculiar facts and to conclude litigation. Ratio vs. Obiter: Ratio - where an authority delays final determination and an application date is established, the authority is entitled to interest on the unearned increase from the application date; the court may fix the rate based on equities (here 9% p.a.). Obiter - remarks on the appropriateness of the specific rate in other factual contexts. Conclusion: The authority is entitled to interest at 9% p.a. on the unearned increase calculated as on 2.7.1985, from that date until payment; the authority must provide necessary calculation within four weeks and the applicant must pay within six weeks thereafter. Issue 5 - Authority's insistence on payment of misuse/compounding charges before approval, and effect on computation of unearned increase Legal framework: The authority may require regularization of misuse, payment of damages/compounding charges, and satisfaction of conditions before granting approval; such requirements are distinct from the computation of unearned increase, which is tied to the date of application. Precedent treatment: The authority argued that approval cannot be granted until misuse is regularized and charges are paid, and that final computation depends on the date of approval. The Court treated these procedural prerequisites as separate from the legal rule governing the date for computing unearned increase. Interpretation and reasoning: The Court recognized the authority's procedural prerequisites but held that such procedural non-completion cannot displace the established rule that unearned increase is computed as of the date of application. Allowing procedural delay to alter the computation date would unfairly prejudice the applicant. Ratio vs. Obiter: Ratio - procedural requirements for approval do not change the legal date for computing unearned increase where an application has been filed; the authority may still require regularization and payment of other charges but must compute unearned increase on the application date. Obiter - observations on separation between computation and regularization processes. Conclusion: The authority may insist on regularization and payment of misuse/compounding charges prior to approval, but such insistence does not impact the computation date for unearned increase, which is the date of application (2.7.1985) in the present facts.