    <title>2023 (4) TMI 1425 - Supreme Court</title>
    <link>https://www.taxtmi.com/caselaws?id=462210</link>
    <description>A power procurement contract with an express change-in-law mechanism did not permit recovery of costs arising from a higher water intake system estimate, because bidders were required to verify site conditions and the pre-bid report was disclaimed as non-binding; an erroneous or inadequate report could not itself create a compensable legal change. The office memorandum dated 17.06.2011 also did not amount to a change in law for customs duty on mining equipment, as the record did not show a pre-existing exemption for captive coal mine imports or a proven shift in the legal position. In both respects, the contractual claims failed.</description>
    <language>en-us</language>
    <pubDate>Thu, 06 Apr 2023 00:00:00 +0530</pubDate>
    <lastBuildDate>Wed, 28 May 2025 17:07:18 +0530</lastBuildDate>
    <generator>TaxTMI RSS Generator</generator>
    <atom:link href="https://www.taxtmi.com/rss_feed_blog?id=825984" rel="self" type="application/rss+xml"/>
    <item>
      <title>2023 (4) TMI 1425 - Supreme Court</title>
      <link>https://www.taxtmi.com/caselaws?id=462210</link>
      <description>A power procurement contract with an express change-in-law mechanism did not permit recovery of costs arising from a higher water intake system estimate, because bidders were required to verify site conditions and the pre-bid report was disclaimed as non-binding; an erroneous or inadequate report could not itself create a compensable legal change. The office memorandum dated 17.06.2011 also did not amount to a change in law for customs duty on mining equipment, as the record did not show a pre-existing exemption for captive coal mine imports or a proven shift in the legal position. In both respects, the contractual claims failed.</description>
      <category>Case-Laws</category>
      <law>Indian Laws</law>
      <pubDate>Thu, 06 Apr 2023 00:00:00 +0530</pubDate>
      <guid isPermaLink="true">https://www.taxtmi.com/caselaws?id=462210</guid>