    <title>2006 (3) TMI 805 - BOMBAY HIGH COURT</title>
    <link>https://www.taxtmi.com/caselaws?id=305779</link>
    <description>The court found the suit maintainable, ruled on breach of contract by both parties, and determined the entitlements and deductions. Plaintiffs were awarded Rs. 1,60,102.55 with 9% interest, while defendants were allowed to deduct Rs. 88,807.45 as liquidated damages. The court rejected unsubstantiated penalty claims and made no cost order.</description>
    <language>en-us</language>
    <pubDate>Fri, 24 Mar 2006 00:00:00 +0530</pubDate>
    <lastBuildDate>Fri, 23 Dec 2022 14:59:41 +0530</lastBuildDate>
    <generator>TaxTMI RSS Generator</generator>
    <atom:link href="https://www.taxtmi.com/rss_feed_blog?id=699577" rel="self" type="application/rss+xml"/>
    <item>
      <title>2006 (3) TMI 805 - BOMBAY HIGH COURT</title>
      <link>https://www.taxtmi.com/caselaws?id=305779</link>
      <description>The court found the suit maintainable, ruled on breach of contract by both parties, and determined the entitlements and deductions. Plaintiffs were awarded Rs. 1,60,102.55 with 9% interest, while defendants were allowed to deduct Rs. 88,807.45 as liquidated damages. The court rejected unsubstantiated penalty claims and made no cost order.</description>
      <category>Case-Laws</category>
      <law>Indian Laws</law>
      <pubDate>Fri, 24 Mar 2006 00:00:00 +0530</pubDate>
      <guid isPermaLink="true">https://www.taxtmi.com/caselaws?id=305779</guid>
    </item>