    <title>2001 (10) TMI 1170 - KARNATAKA HIGH COURT</title>
    <link>https://www.taxtmi.com/caselaws?id=192087</link>
    <description>An arbitral appointment made after the employer missed the contractual time limit was upheld because the contractor was then entitled to proceed under the agreed mechanism, and the employer&#039;s participation without timely objection amounted to waiver. The award was also sustained despite the municipal council not being joined, because the contract and surrounding arrangements showed that the employer undertook project responsibilities and was personally liable, making Section 230 of the Contract Act inapplicable. The Section 34 challenge to interest, compensation, price adjustment, and other monetary reliefs failed because the award was reasoned, evidence-based, and disclosed no statutory ground or public policy breach.</description>
    <language>en-us</language>
    <pubDate>Fri, 19 Oct 2001 00:00:00 +0530</pubDate>
    <lastBuildDate>Fri, 12 May 2017 17:19:10 +0530</lastBuildDate>
    <generator>TaxTMI RSS Generator</generator>
    <atom:link href="https://www.taxtmi.com/rss_feed_blog?id=468492" rel="self" type="application/rss+xml"/>
    <item>
      <title>2001 (10) TMI 1170 - KARNATAKA HIGH COURT</title>
      <link>https://www.taxtmi.com/caselaws?id=192087</link>
      <description>An arbitral appointment made after the employer missed the contractual time limit was upheld because the contractor was then entitled to proceed under the agreed mechanism, and the employer&#039;s participation without timely objection amounted to waiver. The award was also sustained despite the municipal council not being joined, because the contract and surrounding arrangements showed that the employer undertook project responsibilities and was personally liable, making Section 230 of the Contract Act inapplicable. The Section 34 challenge to interest, compensation, price adjustment, and other monetary reliefs failed because the award was reasoned, evidence-based, and disclosed no statutory ground or public policy breach.</description>
      <category>Case-Laws</category>
      <law>Indian Laws</law>
      <pubDate>Fri, 19 Oct 2001 00:00:00 +0530</pubDate>
      <guid isPermaLink="true">https://www.taxtmi.com/caselaws?id=192087</guid>
    </item>