Dear Experts,
We received order to supply of goods to 2 x 660 MW Mega power plant, for which we are reffering to get central excise duty exemption Not No.12/2012 C.Ex, Table Sl.No.338, Condition No.43, Under 43 condition there are 4 paras a, b, c, d. If i fulfilled para 'a' condition, then b, c and d also required fulfill.
Kindly clarify.
Ramesh M
Seeking Central Excise Duty Exemption for Mega Power Project Under Notification No. 12/2012 C.Ex, Table Sl.No.338 A participant in a discussion forum sought advice on obtaining central excise duty exemption for supplying goods to a 2 x 660 MW mega power project. They referenced Notification No. 12/2012 C.Ex, specifically Table Sl.No.338 and Condition No.43, which includes four clauses. An expert advised that clauses a, c, and d must be fulfilled, while clause b applies only if the Joint Secretary's certificate is provisional. The participant inquired about using alternative table numbers for their supply to the Rajasthan state electricity board under ICB and asked about the necessary certificates. (AI Summary)