Tribunal dismisses priority consideration, approves resolution plan under IBC, 2016 The tribunal dismissed the application seeking priority consideration before the approval of the resolution plan, citing that the issue had been settled ...
Cases where this provision is explicitly mentioned in the judgment/order text; may not be exhaustive. To view the complete list of cases mentioning this section, Click here.
Provisions expressly mentioned in the judgment/order text.
Tribunal dismisses priority consideration, approves resolution plan under IBC, 2016
The tribunal dismissed the application seeking priority consideration before the approval of the resolution plan, citing that the issue had been settled by the NCLAT and the applicant failed to prove ineligibility under section 29A of the IBC, 2016. The tribunal also rejected the claim regarding the ineligibility of erstwhile promoters, as the applicant did not provide sufficient evidence. However, the tribunal approved the resolution plan, finding it feasible and compliant with the IBC, 2016, directing the resolution professional to complete formalities and transfer management to the nominated board of directors.
Issues Involved: 1. Priority consideration of application before approval of resolution plan. 2. Ineligibility of erstwhile promoters/suspended management under section 29A of the IBC, 2016. 3. Approval of the resolution plan.
Issue-wise Detailed Analysis:
1. Priority consideration of application before approval of resolution plan: The applicant sought priority consideration of its application before the approval of the resolution plan and prayed for its rejection, alleging the resolution professional failed to assess the applicability of section 29A of the Insolvency and Bankruptcy Code, 2016. The tribunal noted that the corporate debtor was admitted into CIRP on January 22, 2020, and during the process, it was claimed that the erstwhile promoters were ineligible under section 29A of the IBC, 2016. The resolution professional informed that the corporate debtor had been converted into an MSME, making section 29A inapplicable by virtue of section 240A of the IBC, 2016. However, an order dated January 6, 2021, held that the erstwhile promoters were ineligible. The tribunal dismissed the application, stating that the issue had been settled by the National Company Law Appellate Tribunal (NCLAT) and that the applicant failed to prove the ineligibility under section 29A of the IBC, 2016.
2. Ineligibility of erstwhile promoters/suspended management under section 29A of the IBC, 2016: The applicant alleged that the resolution professional did not properly assess the ineligibility of the erstwhile promoters under section 29A of the IBC, 2016. The resolution professional contended that due diligence was conducted as per the IBC, 2016, and regulations, and the suspended management was not ineligible under section 29A(c) since the corporate debtor's account had not been classified as a non-performing asset as of the insolvency commencement date. The tribunal found that the applicant did not bring sufficient material to prove the ineligibility under section 29A and dismissed the claim.
3. Approval of the resolution plan: The tribunal considered the application for the approval of the resolution plan. The corporate debtor was admitted into CIRP on January 22, 2020, and the IRP conducted the CIRP as per the IBC, 2016. The CoC approved the modified resolution plan by 100% vote. The tribunal noted that the resolution plan was feasible and viable, with provisions for paying off creditors and infusing Rs. 15 crores as working capital. The tribunal approved the resolution plan, stating that it complied with the requirements of the IBC, 2016, and regulations, and addressed the causes for failure and measures to run the corporate debtor in the future.
Judgment: The tribunal dismissed I. A. No. 145 of 2021, stating that the applicant failed to prove the ineligibility under section 29A of the IBC, 2016. The tribunal approved the resolution plan in I. A. No. 58 of 2021, granting specific reliefs and concessions while directing the resolution professional to complete the necessary formalities and hand over the management to the nominated board of directors. The tribunal also directed the resolution professional to forward all records to the Insolvency and Bankruptcy Board of India.