Just a moment...
Press 'Enter' to add multiple search terms. Rules for Better Search
Use comma for multiple locations.
---------------- For section wise search only -----------------
Accuracy Level ~ 90%
Press 'Enter' after typing page number.
Press 'Enter' after typing page number.
No Folders have been created
Are you sure you want to delete "My most important" ?
NOTE:
Press 'Enter' after typing page number.
Press 'Enter' after typing page number.
Don't have an account? Register Here
Press 'Enter' after typing page number.
Issues: (i) Whether a writ petition under Articles 226 and 227 of the Constitution of India can be entertained to interfere with an arbitral process or an order passed under Section 16 of the Arbitration and Conciliation Act, 1996; (ii) Whether the dispute arising from the contract was required to be governed by the Gujarat Public Works Contracts Disputes Arbitration Tribunal Act, 1992 instead of the Arbitration and Conciliation Act, 1996.
Issue (i): Whether a writ petition under Articles 226 and 227 of the Constitution of India can be entertained to interfere with an arbitral process or an order passed under Section 16 of the Arbitration and Conciliation Act, 1996.
Analysis: The Arbitration and Conciliation Act, 1996 is a complete code and Section 5 embodies the legislative policy of minimal judicial intervention. The statutory scheme provides specific remedies for appointment, jurisdictional objections, and challenge to an award, including the mechanism under Section 16 and the eventual challenge under Section 34. Interference under Articles 226 and 227 is not barred in the abstract, but it is to be exercised only in exceptional circumstances, such as clear absence of remedy or demonstrable bad faith. No such exceptional circumstance was shown, and the High Court ought not to have interjected the arbitral process at that stage.
Conclusion: The writ interference was not justified and the objection to the arbitrator's jurisdiction had to await the remedy available under Section 34.
Issue (ii): Whether the dispute arising from the contract was required to be governed by the Gujarat Public Works Contracts Disputes Arbitration Tribunal Act, 1992 instead of the Arbitration and Conciliation Act, 1996.
Analysis: The contract was composite in nature, involving manufacture as well as supply of bricks, and whether it answered the definition of a works contract under Section 2(k) of the Gujarat Public Works Contracts Disputes Arbitration Tribunal Act, 1992 required contractual interpretation and evidentiary assessment. Such a determination was not suitable for writ adjudication at the stage when the Section 16 ruling was challenged. The mere invocation of the State enactment did not by itself justify bypassing the arbitral framework under the 1996 Act.
Conclusion: The State enactment did not warrant writ interference with the arbitral proceedings, and the jurisdictional question remained open for consideration in the pending statutory challenge.
Final Conclusion: The appellate court held that judicial intervention at the writ stage was unwarranted and restored the primacy of the arbitral statutory mechanism, leaving the parties to pursue the remedies available under the Arbitration and Conciliation Act, 1996.
Ratio Decidendi: Where a statute creates a complete arbitral code with specific in-built remedies, writ jurisdiction should not be used to interrupt arbitral proceedings except in rare cases of exceptional need or bad faith, and jurisdictional objections should ordinarily be pursued through the statutory challenge mechanism.